QUESTION 001R · PDF p. 16

Which sequence correctly represents the DIKW hierarchy?

  1. A.Data → Information → Knowledge → Wisdom
  2. B.Information → Data → Knowledge → Wisdom
  3. C.Knowledge → Data → Information → Wisdom
  4. D.Data → Knowledge → Information → Wisdom
Answer: A
Data → Information → Knowledge → Wisdom

Data → Information → Knowledge → Wisdom. DIKW moves from raw facts to context, to patterns, to judgement.

Source: answer explanations, p. 67
QUESTION 002U · PDF p. 16

The value “47” stored in a database field becomes information when it…

  1. A.is placed in context, e.g. “47 cartons of PK-1042 at the Hanoi warehouse at end of day 13/09”
  2. B.is printed on paper
  3. C.is entered by a supervisor rather than a clerk
  4. D.is saved in a relational database
Answer: A
is placed in context, e.g. “47 cartons of PK-1042 at the Hanoi warehouse at end of day 13/09”

is placed in context, e.g. “47 cartons of PK-1042 at the Hanoi warehouse at end of day 13/09”. Context and purpose, not storage or medium, distinguish information from data.

Source: answer explanations, p. 67
QUESTION 003R · PDF p. 16

Which list gives the five components of an information system used in this course?

  1. A.Hardware, software, data, people, process
  2. B.Data, information, knowledge, wisdom, decision
  3. C.Hardware, software, network, cloud, data
  4. D.Input, processing, output, storage, feedback
Answer: A
Hardware, software, data, people, process

Hardware, software, data, people, process. The five-component model includes the human and procedural elements, not only technology.

Source: answer explanations, p. 67
QUESTION 004U · PDF p. 16

Which two components most frequently determine whether an IS project succeeds or fails?

  1. A.Software and cloud services
  2. B.Data and network
  3. C.Hardware and software
  4. D.People and process
Answer: D
People and process

People and process. Technology is mature; failures usually come from how people use the system and how work is organised.

Source: answer explanations, p. 67
QUESTION 005R · PDF p. 16

In the input – processing – output model, the mechanism that uses output to adjust input or processing is called…

  1. A.interface
  2. B.feedback
  3. C.storage
  4. D.throughput
Answer: B
feedback

feedback. Feedback closes the loop so that the system can be controlled and corrected.

Source: answer explanations, p. 67
QUESTION 006Ap · PDF p. 16

A courier’s system records every proof-of-delivery scan at the moment it occurs. This is primarily a…

  1. A.management information system (MIS)
  2. B.decision support system (DSS)
  3. C.transaction processing system (TPS)
  4. D.executive support system (ESS)
Answer: C
transaction processing system (TPS)

transaction processing system (TPS). Recording routine daily transactions is the role of a TPS at the operational level.

Source: answer explanations, p. 67
QUESTION 007U · PDF p. 17

An MIS (in the narrow, system-type sense) mainly produces…

  1. A.periodic, structured summary and exception reports for middle managers
  2. B.what-if simulation models for unstructured problems
  3. C.real-time transaction records for clerks
  4. D.external market news for the board
Answer: A
periodic, structured summary and exception reports for middle managers

periodic, structured summary and exception reports for middle managers. MIS summarises TPS data into routine reports supporting tactical control.

Source: answer explanations, p. 67
QUESTION 008U · PDF p. 17

A decision support system (DSS) is designed mainly for…

  1. A.storing master data for the whole enterprise
  2. B.automatic decisions with no human involvement
  3. C.semi-structured decisions, using data, models and what-if analysis
  4. D.fully structured, repetitive transactions
Answer: C
semi-structured decisions, using data, models and what-if analysis

semi-structured decisions, using data, models and what-if analysis. DSS combines models and data to support, not replace, a manager facing a semi-structured choice.

Source: answer explanations, p. 67
QUESTION 009R · PDF p. 17

Which management level does an executive support system (ESS) mainly serve?

  1. A.Clerical
  2. B.Tactical
  3. C.Strategic
  4. D.Operational
Answer: C
Strategic

Strategic. ESS provides aggregated internal and external information to senior executives.

Source: answer explanations, p. 67
QUESTION 010U · PDF p. 17

Moving up the hierarchy from TPS to MIS, DSS and ESS, which statement is correct?

  1. A.Systems depend only on internal transaction data
  2. B.Data become more detailed and decisions more structured
  3. C.Decisions become more routine and repetitive
  4. D.Data become more aggregated and decisions become less structured
Answer: D
Data become more aggregated and decisions become less structured

Data become more aggregated and decisions become less structured. Higher levels use summarised data and external signals for less structured decisions.

Source: answer explanations, p. 67
QUESTION 011U · PDF p. 17

Which statement best distinguishes IT from IS?

  1. A.IT and IS are synonyms
  2. B.An IS is one component of IT
  3. C.IT is the technology (hardware, software, networks); an IS also includes data, people and processes serving an organisational purpose
  4. D.IT includes people and processes, while an IS is only software
Answer: C
IT is the technology (hardware, software, networks); an IS also includes data, people and processes serving an organisational purpose

IT is the technology (hardware, software, networks); an IS also includes data, people and processes serving an organisational purpose. An IS is a socio-technical system; IT is its technical enabler.

Source: answer explanations, p. 67
QUESTION 012R · PDF p. 17

Porter’s three generic competitive strategies are…

  1. A.cost leadership, differentiation and focus
  2. B.cost leadership, integration and outsourcing
  3. C.focus, automation and globalisation
  4. D.differentiation, diversification and digitisation
Answer: A
cost leadership, differentiation and focus

cost leadership, differentiation and focus. These are the three classic generic strategies.

Source: answer explanations, p. 67
QUESTION 013Ap · PDF p. 17

A 3PL uses route optimisation and automated dispatch to reach the lowest cost per delivery in its market. Which strategy does the IS mainly support?

  1. A.Diversification
  2. B.Cost leadership
  3. C.Focus
  4. D.Differentiation
Answer: B
Cost leadership

Cost leadership. Lower unit cost through efficiency is cost leadership.

Source: answer explanations, p. 67
QUESTION 014Ap · PDF p. 18

An express company offers live tracking and precise ETAs that customers value and pay a premium for. Which strategy does the IS mainly support?

  1. A.Focus
  2. B.Cost leadership
  3. C.Differentiation
  4. D.Vertical integration
Answer: C
Differentiation

Differentiation. A distinctive service attribute customers value is differentiation.

Source: answer explanations, p. 67
QUESTION 015R · PDF p. 18

In Porter’s value chain, inbound logistics and outbound logistics are classified as…

  1. A.support activities
  2. B.primary activities
  3. C.competitive forces
  4. D.generic strategies
Answer: B
primary activities

primary activities. Both directly move goods through the firm and are primary activities.

Source: answer explanations, p. 67
QUESTION 016R · PDF p. 18

Which sequence best reflects the historical evolution of business information systems?

  1. A.DSS → TPS → ERP → MIS → ESS
  2. B.Data processing/TPS → MIS → DSS/ESS → ERP and Internet-based e-business → cloud, mobile, big data and AI
  3. C.AI → big data → MIS → TPS → ERP
  4. D.ERP → TPS → cloud → MIS → DSS
Answer: B
Data processing/TPS → MIS → DSS/ESS → ERP and Internet-based e-business → cloud, mobile, big data and AI

Data processing/TPS → MIS → DSS/ESS → ERP and Internet-based e-business → cloud, mobile, big data and AI. IS evolved from automating transactions to reporting, decision support, enterprise integration and data-driven intelligence.

Source: answer explanations, p. 67
QUESTION 017U · PDF p. 18

Which of the following is NOT one of Porter’s five competitive forces?

  1. A.Threat of new entrants
  2. B.Bargaining power of suppliers
  3. C.Threat of substitute products or services
  4. D.The firm’s level of IT spending
Answer: D
The firm’s level of IT spending

The firm’s level of IT spending. The five forces are rivalry, new entrants, substitutes, buyer power and supplier power.

Source: answer explanations, p. 67
QUESTION 018U · PDF p. 18

A stock report reaches the dispatcher three days after the trucks have left. Which quality of useful information is mainly violated?

  1. A.Timeliness
  2. B.Accuracy
  3. C.Completeness
  4. D.Relevance
Answer: A
Timeliness

Timeliness. Correct information that arrives too late cannot support the decision.

Source: answer explanations, p. 67
QUESTION 019An · PDF p. 18

A firm buys a modern WMS, yet stock remains wrong because staff still keep a paper log and key it in at month end. Which component is the root weakness?

  1. A.Network bandwidth
  2. B.Hardware
  3. C.Software
  4. D.Process and people – the way work is performed bypasses the system
Answer: D
Process and people – the way work is performed bypasses the system

Process and people – the way work is performed bypasses the system. The technology exists; the work practice prevents real-time capture.

Source: answer explanations, p. 68
QUESTION 020Ap · PDF p. 19

A mini-MIS turns raw delivery scan records into “on-time delivery rate by route per week”. In the IPO model, this step is…

  1. A.input capture
  2. B.feedback
  3. C.storage only
  4. D.processing that converts data into information
Answer: D
processing that converts data into information

processing that converts data into information. Aggregating and calculating KPIs is processing.

Source: answer explanations, p. 68
SESSION 02 / 15

IT infrastructure for logistics

Questions 21–40 · 20 questions

QUESTION 021R · PDF p. 19

Handheld scanners, servers and RFID readers are examples of which IS component?

  1. A.Hardware
  2. B.Data
  3. C.Process
  4. D.System software
Answer: A
Hardware

Hardware. They are physical devices.

Source: answer explanations, p. 68
QUESTION 022R · PDF p. 19

Which of the following is system software rather than application software?

  1. A.A spreadsheet application
  2. B.An operating system
  3. C.A CRM application
  4. D.A warehouse management system
Answer: B
An operating system

An operating system. The operating system manages hardware resources for applications.

Source: answer explanations, p. 68
QUESTION 023U · PDF p. 19

A three-tier (n-tier) architecture separates…

  1. A.presentation, application (business logic) and data
  2. B.hardware, software and people
  3. C.IaaS, PaaS and SaaS
  4. D.LAN, WAN and the Internet
Answer: A
presentation, application (business logic) and data

presentation, application (business logic) and data. Separating tiers allows each to scale and be secured independently.

Source: answer explanations, p. 68
QUESTION 024R · PDF p. 19

A network that gives selected external partners, such as carriers, secure access to part of a company’s internal systems is…

  1. A.a personal area network
  2. B.an intranet
  3. C.an extranet
  4. D.a LAN
Answer: C
an extranet

an extranet. An extranet extends the intranet to authorised outsiders.

Source: answer explanations, p. 68
QUESTION 025R · PDF p. 19

In Infrastructure as a Service (IaaS), the provider supplies…

  1. A.a complete ready-to-use application
  2. B.only a backup service for spreadsheets
  3. C.on-site staff to run the warehouse
  4. D.virtual servers, storage and networking, while the customer manages the OS and everything above
Answer: D
virtual servers, storage and networking, while the customer manages the OS and everything above

virtual servers, storage and networking, while the customer manages the OS and everything above. IaaS rents raw infrastructure; the customer keeps OS, software and data.

Source: answer explanations, p. 68
QUESTION 026U · PDF p. 20

Under SaaS, the customer remains primarily responsible for…

  1. A.replacing physical servers
  2. B.its own data and user access
  3. C.patching the operating system
  4. D.maintaining the application runtime
Answer: B
its own data and user access

its own data and user access. In SaaS the provider runs everything except the customer’s data and accounts.

Source: answer explanations, p. 68
QUESTION 027Ap · PDF p. 20

A start-up wants to build its own shipment-tracking application but does not want to manage operating systems or middleware. Which model fits best?

  1. A.IaaS
  2. B.SaaS
  3. C.On-premise data centre
  4. D.PaaS
Answer: D
PaaS

PaaS. PaaS provides a managed platform on which the customer deploys its own application.

Source: answer explanations, p. 68
QUESTION 028Ap · PDF p. 20

A small forwarder subscribes to a ready-made TMS accessed via browser for a monthly fee. This is…

  1. A.PaaS
  2. B.a licensed on-premise package
  3. C.IaaS
  4. D.SaaS
Answer: D
SaaS

SaaS. A complete application delivered as a subscription service is SaaS.

Source: answer explanations, p. 68
QUESTION 029U · PDF p. 20

Moving from IaaS to PaaS to SaaS, the customer generally gets…

  1. A.higher upfront capital expenditure
  2. B.more control and more customisation
  3. C.less management work but less customisation and control
  4. D.a need for more in-house infrastructure staff
Answer: C
less management work but less customisation and control

less management work but less customisation and control. Each step to the right hands more of the stack to the provider.

Source: answer explanations, p. 68
QUESTION 030U · PDF p. 20

The main financial difference between cloud and on-premise deployment is that cloud…

  1. A.shifts spending from upfront capital expenditure to recurring operating expenditure
  2. B.requires the customer to purchase servers
  3. C.is always cheaper over any time horizon
  4. D.eliminates all maintenance and security duties
Answer: A
shifts spending from upfront capital expenditure to recurring operating expenditure

shifts spending from upfront capital expenditure to recurring operating expenditure. Cloud is pay-as-you-go; total cost must still be compared over 3–5 years.

Source: answer explanations, p. 68
QUESTION 031U · PDF p. 20

Which situation most justifies keeping a system on-premise?

  1. A.The firm needs to scale up within days for peak season
  2. B.The firm has no IT staff
  3. C.Strict data-control or regulatory requirements and a need for deep customisation, with capable in-house IT
  4. D.The firm wants to avoid upfront investment
Answer: C
Strict data-control or regulatory requirements and a need for deep customisation, with capable in-house IT

Strict data-control or regulatory requirements and a need for deep customisation, with capable in-house IT. On-premise trades higher cost for control; the other options favour cloud.

Source: answer explanations, p. 68
QUESTION 032R · PDF p. 20

The CIA triad of information security stands for…

  1. A.Confidentiality, Integrity, Availability
  2. B.Compliance, Integrity, Accountability
  3. C.Control, Integrity, Authentication
  4. D.Confidentiality, Identification, Authorisation
Answer: A
Confidentiality, Integrity, Availability

Confidentiality, Integrity, Availability. These are the three core security objectives.

Source: answer explanations, p. 68
QUESTION 033Ap · PDF p. 21

An unauthorised change to stock quantities in the WMS mainly violates…

  1. A.scalability
  2. B.availability
  3. C.integrity
  4. D.confidentiality
Answer: C
integrity

integrity. Integrity means data are not modified without authorisation.

Source: answer explanations, p. 68
QUESTION 034Ap · PDF p. 21

A spreadsheet of customer freight rates is leaked to a competitor. Which CIA objective is breached?

  1. A.Authenticity of the carrier
  2. B.Integrity
  3. C.Confidentiality
  4. D.Availability
Answer: C
Confidentiality

Confidentiality. Disclosure to unauthorised parties is a confidentiality breach.

Source: answer explanations, p. 68
QUESTION 035Ap · PDF p. 21

A DDoS attack takes the customs-declaration system offline during working hours. Which objective is mainly affected?

  1. A.Confidentiality
  2. B.Non-repudiation
  3. C.Integrity
  4. D.Availability
Answer: D
Availability

Availability. The data may be intact and secret, but the service cannot be used when needed.

Source: answer explanations, p. 68
QUESTION 036U · PDF p. 21

Ransomware primarily…

  1. A.is a technique for compressing backups
  2. B.affects only paper documents
  3. C.accelerates network traffic
  4. D.encrypts systems or data and demands payment, threatening availability and often confidentiality
Answer: D
encrypts systems or data and demands payment, threatening availability and often confidentiality

encrypts systems or data and demands payment, threatening availability and often confidentiality. Operations stop when systems are encrypted; data may also be exfiltrated.

Source: answer explanations, p. 68
QUESTION 037Ap · PDF p. 21

Which control best limits the damage of a ransomware attack on a WMS?

  1. A.More network bandwidth
  2. B.Regular backups including an offline copy, with tested restores
  3. C.Longer passwords for customers only
  4. D.Larger monitors for operators
Answer: B
Regular backups including an offline copy, with tested restores

Regular backups including an offline copy, with tested restores. An untouched offline copy allows recovery without paying.

Source: answer explanations, p. 68
QUESTION 038U · PDF p. 21

A hybrid cloud is…

  1. A.a backup tape stored off-site
  2. B.a SaaS application installed on laptops
  3. C.a public cloud shared by competitors only
  4. D.a combination of on-premise or private cloud with public cloud, with data and applications moving between them
Answer: D
a combination of on-premise or private cloud with public cloud, with data and applications moving between them

a combination of on-premise or private cloud with public cloud, with data and applications moving between them. Hybrid keeps sensitive workloads in-house while using public cloud elasticity.

Source: answer explanations, p. 68
QUESTION 039U · PDF p. 22

The cloud “shared responsibility model” means…

  1. A.the customer is responsible for the provider’s data centre
  2. B.nobody is responsible for data
  3. C.the provider is responsible for everything
  4. D.the provider secures the cloud infrastructure, while the customer secures its data, access and configuration in the cloud
Answer: D
the provider secures the cloud infrastructure, while the customer secures its data, access and configuration in the cloud

the provider secures the cloud infrastructure, while the customer secures its data, access and configuration in the cloud. Misconfigured access by the customer remains the customer’s risk.

Source: answer explanations, p. 69
QUESTION 040An · PDF p. 22

A cloud WMS outage stops picking at three warehouses for a full day. Which consideration should have weighed most when selecting and designing the solution?

  1. A.The number of report templates
  2. B.The price of spreadsheet licences
  3. C.Availability: the SLA, redundancy and an offline or fallback mode for critical operations
  4. D.The colour scheme of the user interface
Answer: C
Availability: the SLA, redundancy and an offline or fallback mode for critical operations

Availability: the SLA, redundancy and an offline or fallback mode for critical operations. For operational systems, availability requirements and fallback procedures are critical non-functional criteria.

Source: answer explanations, p. 69
SESSION 03 / 15

Databases and analytics

Questions 41–60 · 20 questions

QUESTION 041R · PDF p. 22

Which sequence shows the data hierarchy in ascending order?

  1. A.Bit → byte → field → record → file (table) → database
  2. B.Database → table → record → field → byte → bit
  3. C.Byte → bit → record → field → database → file
  4. D.Field → bit → byte → table → record → database
Answer: A
Bit → byte → field → record → file (table) → database

Bit → byte → field → record → file (table) → database. Each level groups units of the level below.

Source: answer explanations, p. 69
QUESTION 042R · PDF p. 22

A primary key is…

  1. A.one or more attributes that uniquely identify each record in a table
  2. B.a password protecting the database
  3. C.the first column of any spreadsheet
  4. D.a field that may contain duplicates to speed up searches
Answer: A
one or more attributes that uniquely identify each record in a table

one or more attributes that uniquely identify each record in a table. Uniqueness is the defining property of a primary key.

Source: answer explanations, p. 69
QUESTION 043U · PDF p. 22

A foreign key is used to…

  1. A.encrypt sensitive fields
  2. B.sort a table alphabetically
  3. C.identify each record uniquely within its own table
  4. D.reference the primary key of another table and implement a relationship
Answer: D
reference the primary key of another table and implement a relationship

reference the primary key of another table and implement a relationship. For example, Order.customer_id references Customer.customer_id.

Source: answer explanations, p. 69
QUESTION 044Ap · PDF p. 22

One customer places many orders; each order belongs to exactly one customer. The cardinality is…

  1. A.one-to-one (1:1)
  2. B.one-to-many (1:N)
  3. C.many-to-many (M:N)
  4. D.zero-to-zero
Answer: B
one-to-many (1:N)

one-to-many (1:N). The foreign key customer_id sits on the “many” side (Order).

Source: answer explanations, p. 69
QUESTION 045Ap · PDF p. 23

An order contains many products and a product appears on many orders. How is this implemented in a relational database?

  1. A.By merging the Order and Product tables
  2. B.By duplicating the Product table for each order
  3. C.By listing all product codes in one text field of Order
  4. D.With an associative table such as OrderLine holding both foreign keys plus quantity
Answer: D
With an associative table such as OrderLine holding both foreign keys plus quantity

With an associative table such as OrderLine holding both foreign keys plus quantity. An M:N relationship is resolved into two 1:N relationships through a junction table.

Source: answer explanations, p. 69
QUESTION 046U · PDF p. 23

Which is NOT a typical function of a database management system (DBMS)?

  1. A.Access control and security
  2. B.Data definition and data manipulation (e.g. SQL)
  3. C.Planning daily delivery routes for drivers
  4. D.Backup, recovery and concurrency control
Answer: C
Planning daily delivery routes for drivers

Planning daily delivery routes for drivers. Route planning is an application (TMS) function, not a DBMS function.

Source: answer explanations, p. 69
QUESTION 047U · PDF p. 23

Which statement correctly contrasts OLTP and OLAP?

  1. A.OLTP stores history; OLAP records new orders
  2. B.OLTP is used only by executives; OLAP only by clerks
  3. C.They are two names for the same database
  4. D.OLTP handles many small real-time transactions; OLAP handles complex queries aggregating large volumes of history
Answer: D
OLTP handles many small real-time transactions; OLAP handles complex queries aggregating large volumes of history

OLTP handles many small real-time transactions; OLAP handles complex queries aggregating large volumes of history. Different workloads require differently optimised systems.

Source: answer explanations, p. 69
QUESTION 048Ap · PDF p. 23

“Compare monthly on-time delivery across 12 months and 7 routes” is a typical workload for…

  1. A.A barcode scanner
  2. B.An EDI despatch advice
  3. C.OLTP on the order-entry database
  4. D.OLAP on a data warehouse
Answer: D
OLAP on a data warehouse

OLAP on a data warehouse. It aggregates historical data across dimensions.

Source: answer explanations, p. 69
QUESTION 049R · PDF p. 23

ETL stands for…

  1. A.Enter, Test, Launch
  2. B.Extract, Transform, Load
  3. C.Encrypt, Transfer, Lock
  4. D.Evaluate, Track, Log
Answer: B
Extract, Transform, Load

Extract, Transform, Load. ETL moves and cleans data from sources into a warehouse.

Source: answer explanations, p. 69
QUESTION 050U · PDF p. 23

A data warehouse is best described as…

  1. A.the live operational database edited by clerks all day
  2. B.a backup copy of the ERP
  3. C.a collection of personal spreadsheets
  4. D.a subject-oriented, integrated, time-variant and non-volatile store of historical data for analysis
Answer: D
a subject-oriented, integrated, time-variant and non-volatile store of historical data for analysis

a subject-oriented, integrated, time-variant and non-volatile store of historical data for analysis. These four properties are the classic definition of a data warehouse.

Source: answer explanations, p. 69
QUESTION 051U · PDF p. 24

A data mart is…

  1. A.an online shop selling data
  2. B.the physical server room
  3. C.a subset of the warehouse focused on one function or department, e.g. transport
  4. D.a type of RFID tag
Answer: C
a subset of the warehouse focused on one function or department, e.g. transport

a subset of the warehouse focused on one function or department, e.g. transport. Data marts serve focused analytical needs.

Source: answer explanations, p. 69
QUESTION 052R · PDF p. 24

The five Vs of big data are…

  1. A.Volume, Vendor, Version, Visibility, Value
  2. B.Volume, Velocity, Variety, Veracity, Value
  3. C.Value, Volume, Voice, Video, Vector
  4. D.Velocity, Validation, Virtualisation, Variety, Vision
Answer: B
Volume, Velocity, Variety, Veracity, Value

Volume, Velocity, Variety, Veracity, Value. These five characteristics describe big data.

Source: answer explanations, p. 69
QUESTION 053U · PDF p. 24

Which “V” ultimately decides whether collecting and storing data is worthwhile?

  1. A.Variety
  2. B.Volume
  3. C.Velocity
  4. D.Value
Answer: D
Value

Value. Data without value is only a storage cost.

Source: answer explanations, p. 69
QUESTION 054Ap · PDF p. 24

The same customer exists under three different codes in the master data. Which data quality dimension is violated?

  1. A.Availability
  2. B.Timeliness
  3. C.Uniqueness (no duplicate entities)
  4. D.Velocity
Answer: C
Uniqueness (no duplicate entities)

Uniqueness (no duplicate entities). Duplicates break credit control and per-customer reporting.

Source: answer explanations, p. 69
QUESTION 055Ap · PDF p. 24

A delivery date recorded as 31/02/2026 violates which dimension?

  1. A.Uniqueness
  2. B.Validity
  3. C.Completeness
  4. D.Confidentiality
Answer: B
Validity

Validity. The value does not conform to the allowed format or domain.

Source: answer explanations, p. 69
QUESTION 056Ap · PDF p. 24

15% of order records have no actual delivery date. Which dimension is mainly affected?

  1. A.Uniqueness
  2. B.Variety
  3. C.Validity
  4. D.Completeness
Answer: D
Completeness

Completeness. Required values are missing.

Source: answer explanations, p. 69
QUESTION 057U · PDF p. 24

Data governance mainly refers to…

  1. A.roles, policies, standards and accountabilities (e.g. named data owners) for managing data quality and use
  2. B.buying a faster database server
  3. C.letting every user edit master data freely
  4. D.deleting old data every month
Answer: A
roles, policies, standards and accountabilities (e.g. named data owners) for managing data quality and use

roles, policies, standards and accountabilities (e.g. named data owners) for managing data quality and use. Governance defines who may create, change and approve data.

Source: answer explanations, p. 69
QUESTION 058U · PDF p. 25

Which statement correctly distinguishes master data from transaction data?

  1. A.There is no practical difference
  2. B.Master data exist only in spreadsheets
  3. C.Master data change every second; transactions never change
  4. D.Master data are relatively stable reference entities (items, customers, locations); transactions are events that reference them (orders, receipts)
Answer: D
Master data are relatively stable reference entities (items, customers, locations); transactions are events that reference them (orders, receipts)

Master data are relatively stable reference entities (items, customers, locations); transactions are events that reference them (orders, receipts). Every transaction points at master data, so errors there propagate everywhere.

Source: answer explanations, p. 70
QUESTION 059R · PDF p. 25

Which sequence gives the four levels of analytics in increasing sophistication?

  1. A.Diagnostic → descriptive → predictive → prescriptive
  2. B.Predictive → descriptive → prescriptive → diagnostic
  3. C.Descriptive → diagnostic → predictive → prescriptive
  4. D.Prescriptive → predictive → diagnostic → descriptive
Answer: C
Descriptive → diagnostic → predictive → prescriptive

Descriptive → diagnostic → predictive → prescriptive. From what happened, to why, to what will happen, to what to do.

Source: answer explanations, p. 70
QUESTION 060An · PDF p. 25

Why do organisations keep OLTP systems and the data warehouse separate, linked by ETL?

  1. A.Because the law forbids storing history in one place
  2. B.Because SQL cannot run on a data warehouse
  3. C.Because OLTP systems cannot store numbers
  4. D.Heavy analytical queries would slow operational transactions, and the two are optimised for different workloads and data structures
Answer: D
Heavy analytical queries would slow operational transactions, and the two are optimised for different workloads and data structures

Heavy analytical queries would slow operational transactions, and the two are optimised for different workloads and data structures. Separation protects operational performance and enables integrated historical analysis.

Source: answer explanations, p. 70
SESSION 04 / 15

Enterprise applications and ERP

Questions 61–80 · 20 questions

QUESTION 061R · PDF p. 25

What is the defining feature of an ERP system?

  1. A.It runs only on spreadsheets
  2. B.Many separate departmental databases
  3. C.A single shared database used by all modules
  4. D.It is only an accounting tool
Answer: C
A single shared database used by all modules

A single shared database used by all modules. Integration of data, not the number of features, defines ERP.

Source: answer explanations, p. 70
QUESTION 062U · PDF p. 25

Which is a direct consequence of data silos in a logistics company?

  1. A.Decisions become faster
  2. B.Data are re-entered several times and departments disagree on the numbers
  3. C.Integration costs fall to zero
  4. D.Every department sees the same real-time order status
Answer: B
Data are re-entered several times and departments disagree on the numbers

Data are re-entered several times and departments disagree on the numbers. Disconnected systems produce duplication, conflict and blindness.

Source: answer explanations, p. 70
QUESTION 063Ap · PDF p. 25

How many links may point-to-point integration require to connect 6 systems with each other?

  1. A.15
  2. B.6
  3. C.36
  4. D.12
Answer: A
15

15. n(n−1)/2 = 6 × 5 / 2 = 15.

Source: answer explanations, p. 70
QUESTION 064U · PDF p. 26

The main advantage of an enterprise service bus (ESB) or API hub over point-to-point wiring is that…

  1. A.it guarantees that no system will ever fail
  2. B.it removes the need for any data standard
  3. C.it replaces all business processes
  4. D.each new system needs only one link, and standards, monitoring and error handling are centralised
Answer: D
each new system needs only one link, and standards, monitoring and error handling are centralised

each new system needs only one link, and standards, monitoring and error handling are centralised. A hub turns quadratic complexity into linear complexity.

Source: answer explanations, p. 70
QUESTION 065R · PDF p. 26

Which of the following is NOT a typical core ERP module?

  1. A.Procurement
  2. B.Inventory and warehouse
  3. C.Graphic design for advertising banners
  4. D.Finance and accounting
Answer: C
Graphic design for advertising banners

Graphic design for advertising banners. ERP covers core cross-functional processes, not niche creative tasks.

Source: answer explanations, p. 70
QUESTION 066R · PDF p. 26

Which sequence correctly represents the order-to-cash flow in ERP?

  1. A.Capture order → check/reserve stock → pick and pack → dispatch/deliver → invoice and book revenue → update KPIs
  2. B.Deliver → pick → capture order → reserve stock → invoice
  3. C.Pick and pack → capture order → update KPIs → invoice → reserve stock
  4. D.Invoice → capture order → deliver → reserve stock → pick
Answer: A
Capture order → check/reserve stock → pick and pack → dispatch/deliver → invoice and book revenue → update KPIs

Capture order → check/reserve stock → pick and pack → dispatch/deliver → invoice and book revenue → update KPIs. The order flows through Sales, Inventory, Warehouse, Logistics, Finance and Analytics.

Source: answer explanations, p. 70
QUESTION 067Ap · PDF p. 26

In a process-to-module mapping table, the step “reserve stock for the order” belongs to which ERP module?

  1. A.Inventory
  2. B.Human resources
  3. C.CRM marketing
  4. D.Finance
Answer: A
Inventory

Inventory. Stock availability and reservation are inventory functions.

Source: answer explanations, p. 70
QUESTION 068Ap · PDF p. 26

In the same mapping, “issue the invoice and book revenue” belongs to…

  1. A.Procurement
  2. B.Finance and accounting
  3. C.Warehouse
  4. D.Manufacturing
Answer: B
Finance and accounting

Finance and accounting. Invoicing and revenue posting are finance functions.

Source: answer explanations, p. 70
QUESTION 069U · PDF p. 26

Why does a single shared database give ERP its main advantage?

  1. A.Data entered once are instantly visible to every module, giving one version of the truth and end-to-end visibility
  2. B.It makes the software cheaper to license
  3. C.It removes the need for user training
  4. D.It allows each department to keep its own numbers
Answer: A
Data entered once are instantly visible to every module, giving one version of the truth and end-to-end visibility

Data entered once are instantly visible to every module, giving one version of the truth and end-to-end visibility. Shared data eliminate duplication and conflict.

Source: answer explanations, p. 70
QUESTION 070U · PDF p. 27

What is the most common root cause of ERP project failure?

  1. A.Too little data to process
  2. B.Insufficient network speed
  3. C.People and process issues: resistance, over-customisation, poor data migration and weak management
  4. D.Defects in the database engine
Answer: C
People and process issues: resistance, over-customisation, poor data migration and weak management

People and process issues: resistance, over-customisation, poor data migration and weak management. Change management, not code, usually decides success.

Source: answer explanations, p. 70
QUESTION 071R · PDF p. 27

Which vendors are classified as Tier 1 for large enterprises?

  1. A.MISA AMIS and FAST
  2. B.SAP and Oracle
  3. C.Odoo and ERPNext
  4. D.Base and Bravo
Answer: B
SAP and Oracle

SAP and Oracle. Tier 1 suites are powerful and complete but expensive and slow to deploy.

Source: answer explanations, p. 70
QUESTION 072R · PDF p. 27

Which ERP products are Vietnamese solutions that fit local accounting and tax rules?

  1. A.Salesforce, Celonis
  2. B.Microsoft Dynamics, Infor
  3. C.MISA AMIS, FAST, Bravo, Base
  4. D.SAP S/4HANA, Oracle Fusion
Answer: C
MISA AMIS, FAST, Bravo, Base

MISA AMIS, FAST, Bravo, Base. Local vendors address Vietnamese accounting and tax requirements.

Source: answer explanations, p. 70
QUESTION 073R · PDF p. 27

Which ERP products are open source and suited to SMEs with in-house skills?

  1. A.Odoo and ERPNext
  2. B.Epicor and Infor
  3. C.FAST and Bravo
  4. D.SAP and Oracle
Answer: A
Odoo and ERPNext

Odoo and ERPNext. Open-source ERP is flexible and low cost but requires internal skills.

Source: answer explanations, p. 70
QUESTION 074U · PDF p. 27

According to the lecture, which ERP deployment model is today’s default?

  1. A.Paper-based ledgers
  2. B.Separate spreadsheets per department
  3. C.Cloud ERP on subscription
  4. D.On-premise servers in every branch
Answer: C
Cloud ERP on subscription

Cloud ERP on subscription. Cloud ERP is fast to deploy and paid as you go.

Source: answer explanations, p. 70
QUESTION 075R · PDF p. 27

Which sequence gives the ERP implementation lifecycle?

  1. A.Plan → Design → Build → Test → Deploy → Support
  2. B.Test → Build → Design → Plan → Deploy → Support
  3. C.Design → Deploy → Plan → Test → Build → Support
  4. D.Build → Plan → Deploy → Design → Test → Support
Answer: A
Plan → Design → Build → Test → Deploy → Support

Plan → Design → Build → Test → Deploy → Support. Change management and data run across all six phases.

Source: answer explanations, p. 70
QUESTION 076U · PDF p. 27

Which task is described as the “quiet make-or-break task” of an ERP implementation?

  1. A.Printing the user manual
  2. B.Buying new office furniture
  3. C.Data migration
  4. D.Choosing the logo for the login page
Answer: C
Data migration

Data migration. Dirty migrated data destroy trust in the new system from day one.

Source: answer explanations, p. 70
QUESTION 077U · PDF p. 28

Why is over-customisation of an ERP a risk?

  1. A.It forces the firm to adopt best practices
  2. B.It reduces the number of modules available
  3. C.It makes processes too standardised
  4. D.It increases complexity, cost and time, and makes future upgrades harder
Answer: D
It increases complexity, cost and time, and makes future upgrades harder

It increases complexity, cost and time, and makes future upgrades harder. ERP value comes partly from standard best-practice processes; heavy customisation erodes it.

Source: answer explanations, p. 71
QUESTION 078Ap · PDF p. 28

What is the main lesson of Nestlé’s GLOBE programme?

  1. A.ERP can be deployed globally in a few weeks
  2. B.Standardising processes and master data across many countries brings unified data and efficient procurement, but requires years and very large investment
  3. C.Local systems should never be replaced
  4. D.Product codes do not matter for ERP
Answer: B
Standardising processes and master data across many countries brings unified data and efficient procurement, but requires years and very large investment

Standardising processes and master data across many countries brings unified data and efficient procurement, but requires years and very large investment. The case shows both the reward and the cost of global standardisation.

Source: answer explanations, p. 71
QUESTION 079Ap · PDF p. 28

In the Vinamilk case, which combination supported the farm-to-shelf chain?

  1. A.SAP ERP combined with a nationwide distribution management system (DMS)
  2. B.Only spreadsheets and email
  3. C.Blockchain without ERP
  4. D.A single standalone TMS
Answer: A
SAP ERP combined with a nationwide distribution management system (DMS)

SAP ERP combined with a nationwide distribution management system (DMS). ERP covered finance, manufacturing, inventory and sales; DMS extended to distribution.

Source: answer explanations, p. 71
QUESTION 080An · PDF p. 28

A logistics SME runs purchasing, warehouse and accounting on separate spreadsheets and wants an ERP. Which first step is most appropriate?

  1. A.Map the processes and clean the master data, then select an ERP that fits with minimal customisation and a phased rollout
  2. B.Buy the most expensive Tier 1 suite immediately
  3. C.Go live in all departments at once without testing
  4. D.Customise the ERP to replicate every spreadsheet
Answer: A
Map the processes and clean the master data, then select an ERP that fits with minimal customisation and a phased rollout

Map the processes and clean the master data, then select an ERP that fits with minimal customisation and a phased rollout. Process clarity and clean data precede software; customisation and big-bang risk should be minimised.

Source: answer explanations, p. 71
SESSION 05 / 15

CRM and SRM

Questions 81–100 · 20 questions

QUESTION 081R · PDF p. 28

Which definition best describes CRM?

  1. A.A tool for optimising truck routes
  2. B.An accounting ledger for receivables only
  3. C.A strategy and system for managing all interactions with current and potential customers to increase satisfaction, loyalty and revenue
  4. D.A database of supplier invoices
Answer: C
A strategy and system for managing all interactions with current and potential customers to increase satisfaction, loyalty and revenue

A strategy and system for managing all interactions with current and potential customers to increase satisfaction, loyalty and revenue. CRM is both strategy and technology focused on the customer.

Source: answer explanations, p. 71
QUESTION 082R · PDF p. 28

The three types of CRM are…

  1. A.inbound, outbound and reverse
  2. B.operational, analytical and collaborative
  3. C.strategic, tactical and operational
  4. D.public, private and hybrid
Answer: B
operational, analytical and collaborative

operational, analytical and collaborative. Capture, understand, then act consistently.

Source: answer explanations, p. 71
QUESTION 083Ap · PDF p. 29

Which CRM type predicts customer churn?

  1. A.Operational CRM
  2. B.Supplier CRM
  3. C.Collaborative CRM
  4. D.Analytical CRM
Answer: D
Analytical CRM

Analytical CRM. Churn prediction is analysis of captured history.

Source: answer explanations, p. 71
QUESTION 084Ap · PDF p. 29

Automatic confirmation emails and support tickets belong to which CRM type?

  1. A.Analytical CRM
  2. B.Operational CRM
  3. C.Strategic CRM
  4. D.Collaborative CRM
Answer: B
Operational CRM

Operational CRM. Operational CRM automates daily interactions where data are created.

Source: answer explanations, p. 71
QUESTION 085Ap · PDF p. 29

A customer receives the same consistent service whether calling, chatting, ordering online or visiting a store. Which CRM type enables this?

  1. A.Operational CRM
  2. B.Collaborative CRM
  3. C.Analytical CRM
  4. D.SRM
Answer: B
Collaborative CRM

Collaborative CRM. Collaborative CRM shares customer information across channels.

Source: answer explanations, p. 71
QUESTION 086R · PDF p. 29

Which sequence is the customer lifecycle presented in the lecture?

  1. A.Serve → Reach → Advocate → Acquire → Retain
  2. B.Retain → Serve → Acquire → Reach → Advocate
  3. C.Reach → Acquire → Serve → Retain → Advocate
  4. D.Acquire → Advocate → Reach → Serve → Retain
Answer: C
Reach → Acquire → Serve → Retain → Advocate

Reach → Acquire → Serve → Retain → Advocate. Advocates refer others, looping back to reach.

Source: answer explanations, p. 71
QUESTION 087U · PDF p. 29

The main purpose of a 360° customer view is to…

  1. A.consolidate contact, order, support, complaint and channel history into one profile so staff answer without making the customer repeat information
  2. B.list all suppliers by price
  3. C.replace the ERP database
  4. D.show the warehouse layout in 3D
Answer: A
consolidate contact, order, support, complaint and channel history into one profile so staff answer without making the customer repeat information

consolidate contact, order, support, complaint and channel history into one profile so staff answer without making the customer repeat information. One screen answers the customer.

Source: answer explanations, p. 71
QUESTION 088U · PDF p. 29

Why does CRM emphasise retention?

  1. A.Keeping an existing customer costs far less than winning a new one
  2. B.New customers are never profitable
  3. C.Retention requires no data
  4. D.Law requires firms to keep customers
Answer: A
Keeping an existing customer costs far less than winning a new one

Keeping an existing customer costs far less than winning a new one. Loyalty is cheaper than acquisition.

Source: answer explanations, p. 71
QUESTION 089R · PDF p. 29

The three main areas of SRM are…

  1. A.planning, execution and settlement of transport
  2. B.marketing, sales and service
  3. C.sourcing, procurement and supplier performance
  4. D.picking, packing and shipping
Answer: C
sourcing, procurement and supplier performance

sourcing, procurement and supplier performance. SRM manages the inbound, supply side of the chain.

Source: answer explanations, p. 71
QUESTION 090R · PDF p. 30

Which sequence is the e-procurement process?

  1. A.Payment → purchase order → requisition → receipt → approval
  2. B.Receipt → payment → requisition → approval → purchase order
  3. C.Approval → payment → receipt → requisition → invoice matching
  4. D.Requisition → approval → purchase order → receipt → invoice matching → payment
Answer: D
Requisition → approval → purchase order → receipt → invoice matching → payment

Requisition → approval → purchase order → receipt → invoice matching → payment. Each step leaves an audit trail.

Source: answer explanations, p. 71
QUESTION 091R · PDF p. 30

Three-way matching compares…

  1. A.three months of sales
  2. B.three carriers’ delivery times
  3. C.three suppliers’ prices
  4. D.the purchase order, the goods receipt and the supplier invoice
Answer: D
the purchase order, the goods receipt and the supplier invoice

the purchase order, the goods receipt and the supplier invoice. Payment is released only when what was ordered, received and invoiced agree.

Source: answer explanations, p. 71
QUESTION 092Ap · PDF p. 30

A supplier scorecard uses weights of 30% on-time, 30% quality, 25% price and 15% responsiveness. Supplier A scores 95, 93, 88 and 90 respectively. What is its weighted score?

  1. A.91.9
  2. B.90.0
  3. C.93.4
  4. D.91.5
Answer: A
91.9

91.9. 0.30×95 + 0.30×93 + 0.25×88 + 0.15×90 = 28.5 + 27.9 + 22.0 + 13.5 = 91.9 (≈92).

Source: answer explanations, p. 71
QUESTION 093U · PDF p. 30

How should scorecard weights be set?

  1. A.Equally for all criteria in every industry
  2. B.By the supplier itself
  3. C.According to strategy, e.g. a pharmaceutical firm weights quality, an e-commerce firm weights on-time delivery
  4. D.Randomly each quarter
Answer: C
According to strategy, e.g. a pharmaceutical firm weights quality, an e-commerce firm weights on-time delivery

According to strategy, e.g. a pharmaceutical firm weights quality, an e-commerce firm weights on-time delivery. Weights force the organisation to state what it values.

Source: answer explanations, p. 71
QUESTION 094U · PDF p. 30

Which use of a supplier score is consistent with the lecture?

  1. A.Allocate more volume to high scorers, use scores in negotiation, and place weak suppliers on an improvement plan or exit
  2. B.Use scores only for decoration in reports
  3. C.Publish scores on social media
  4. D.Pay the lowest scorer first
Answer: A
Allocate more volume to high scorers, use scores in negotiation, and place weak suppliers on an improvement plan or exit

Allocate more volume to high scorers, use scores in negotiation, and place weak suppliers on an improvement plan or exit. The score must drive decisions.

Source: answer explanations, p. 72
QUESTION 095U · PDF p. 30

In the extended enterprise, which arrangement is correct?

  1. A.All three are independent with no data flow
  2. B.CRM upstream, SRM downstream, ERP outside
  3. C.ERP upstream, CRM in the middle, SRM downstream
  4. D.SRM upstream with suppliers, ERP as the core single source of truth, CRM downstream with customers
Answer: D
SRM upstream with suppliers, ERP as the core single source of truth, CRM downstream with customers

SRM upstream with suppliers, ERP as the core single source of truth, CRM downstream with customers. Goods flow to the customer; demand and information flow back.

Source: answer explanations, p. 72
QUESTION 096R · PDF p. 31

Which metrics are typical of SRM rather than CRM?

  1. A.Customer satisfaction score
  2. B.Supplier on-time rate, defect rate and cost savings
  3. C.Cross-sell conversion rate
  4. D.Customer retention and lifetime value
Answer: B
Supplier on-time rate, defect rate and cost savings

Supplier on-time rate, defect rate and cost savings. SRM aims to cut cost and supply risk.

Source: answer explanations, p. 72
QUESTION 097U · PDF p. 31

What is the lesson of Amazon’s CRM case?

  1. A.Personalisation is impossible at scale
  2. B.Good CRM stands on operational data, not marketing data alone
  3. C.CRM works without any customer data
  4. D.CRM should be isolated from logistics systems
Answer: B
Good CRM stands on operational data, not marketing data alone

Good CRM stands on operational data, not marketing data alone. Recommendations and self-service tracking require integration with operations.

Source: answer explanations, p. 72
QUESTION 098U · PDF p. 31

Toyota’s just-in-time supplier relationships illustrate which trade-off?

  1. A.Short-term contracts with constantly changing suppliers
  2. B.Low inventory cost and stable quality at the price of higher disruption risk
  3. C.High inventory but no supplier relationship
  4. D.Lower quality but zero risk
Answer: B
Low inventory cost and stable quality at the price of higher disruption risk

Low inventory cost and stable quality at the price of higher disruption risk. With almost no buffer stock, one late supplier stops the line.

Source: answer explanations, p. 72
QUESTION 099Ap · PDF p. 31

Purchase requests above 50 million VND are automatically routed to the director, others to the department head. This is a feature of…

  1. A.route optimisation in TMS
  2. B.e-procurement approval routing in SRM
  3. C.slotting in WMS
  4. D.analytical CRM
Answer: B
e-procurement approval routing in SRM

e-procurement approval routing in SRM. Approval by spending threshold is a standard e-procurement control.

Source: answer explanations, p. 72
QUESTION 100An · PDF p. 31

An express delivery firm must choose whether to invest first in CRM or SRM. Which reasoning is most defensible?

  1. A.Always CRM, because revenue matters more than cost
  2. B.Prioritise the system addressing the measured binding problem, e.g. SRM if subcontracted carriers drive late deliveries, CRM if churn is the main loss
  3. C.Always SRM, because suppliers come first in the chain
  4. D.Choose whichever has the cheaper licence
Answer: B
Prioritise the system addressing the measured binding problem, e.g. SRM if subcontracted carriers drive late deliveries, CRM if churn is the main loss

Prioritise the system addressing the measured binding problem, e.g. SRM if subcontracted carriers drive late deliveries, CRM if churn is the main loss. Investment should follow evidence about where value is lost.

Source: answer explanations, p. 72
SESSION 06 / 15

WMS and TMS

Questions 101–120 · 20 questions

QUESTION 101R · PDF p. 31

Which sequence gives the core WMS process?

  1. A.Picking → receiving → shipping → put-away → packing → storage
  2. B.Receiving → put-away → storage → picking → packing → shipping
  3. C.Shipping → packing → picking → storage → put-away → receiving
  4. D.Packing → storage → receiving → shipping → picking → put-away
Answer: B
Receiving → put-away → storage → picking → packing → shipping

Receiving → put-away → storage → picking → packing → shipping. Goods enter, are stored, then picked, packed and shipped.

Source: answer explanations, p. 72
QUESTION 102R · PDF p. 31

Which warehouse step is the most labour-intensive?

  1. A.Receiving
  2. B.Shipping
  3. C.Picking
  4. D.Put-away
Answer: C
Picking

Picking. Staff must travel to retrieve each item, so picking dominates labour time.

Source: answer explanations, p. 72
QUESTION 103U · PDF p. 32

Placing class-A fast movers in “golden” locations near dispatch is called…

  1. A.cross-docking
  2. B.slotting
  3. C.kitting
  4. D.cycle counting
Answer: B
slotting

slotting. Slotting positions SKUs to cut pick travel.

Source: answer explanations, p. 72
QUESTION 104Ap · PDF p. 32

Six SKUs sorted by weekly picks have cumulative shares of 40%, 65%, 80%, 90%, 95% and 100%. Under the 80/20 rule, which SKUs are class A?

  1. A.The first five SKUs
  2. B.The last three SKUs
  3. C.The first three SKUs (cumulative up to 80%)
  4. D.Only the first SKU
Answer: C
The first three SKUs (cumulative up to 80%)

The first three SKUs (cumulative up to 80%). Class A comprises the items generating about 80% of picks.

Source: answer explanations, p. 72
QUESTION 105U · PDF p. 32

Cross-docking means…

  1. A.returning goods to the supplier
  2. B.counting stock by crossing out lines on paper
  3. C.inbound goods flow directly to outbound vehicles with little or no storage
  4. D.storing goods on both sides of an aisle
Answer: C
inbound goods flow directly to outbound vehicles with little or no storage

inbound goods flow directly to outbound vehicles with little or no storage. It minimises storage time and handling.

Source: answer explanations, p. 72
QUESTION 106U · PDF p. 32

Batch picking improves productivity by…

  1. A.packing before picking
  2. B.collecting items for many orders in one pass, reducing travel per order line
  3. C.storing goods in batches by supplier
  4. D.picking one order at a time to avoid mistakes
Answer: B
collecting items for many orders in one pass, reducing travel per order line

collecting items for many orders in one pass, reducing travel per order line. Shared trips spread travel time across orders.

Source: answer explanations, p. 72
QUESTION 107R · PDF p. 32

FEFO stands for…

  1. A.First-Entry-Final-Output
  2. B.First-Expiry-First-Out, used for perishables
  3. C.Fixed-Equipment-For-Operations
  4. D.Fast-Emergency-Freight-Order
Answer: B
First-Expiry-First-Out, used for perishables

First-Expiry-First-Out, used for perishables. Items expiring first are shipped first.

Source: answer explanations, p. 72
QUESTION 108U · PDF p. 32

Cycle counting differs from a traditional annual stocktake in that it…

  1. A.is only used for empty locations
  2. B.counts everything once a year with the warehouse closed
  3. C.counts part of the inventory continuously without shutting down operations
  4. D.never compares system and physical stock
Answer: C
counts part of the inventory continuously without shutting down operations

counts part of the inventory continuously without shutting down operations. Continuous partial counts keep accuracy high with less disruption.

Source: answer explanations, p. 72
QUESTION 109R · PDF p. 32

“Dock-to-stock” time measures…

  1. A.the time a truck spends on the road
  2. B.the time to pay a supplier
  3. C.the share of cube actually used
  4. D.the time from receiving goods at the dock until they are put away and available
Answer: D
the time from receiving goods at the dock until they are put away and available

the time from receiving goods at the dock until they are put away and available. The lecture’s reference level is under two hours.

Source: answer explanations, p. 72
QUESTION 110Ap · PDF p. 33

A cycle count checks 10,000 locations; 9,950 match the system. What is inventory record accuracy?

  1. A.95.0%
  2. B.99.95%
  3. C.0.5%
  4. D.99.5%
Answer: D
99.5%

99.5%. 9,950 / 10,000 = 99.5%, which equals the lecture’s reference level.

Source: answer explanations, p. 72
QUESTION 111R · PDF p. 33

The four core functions of a TMS are…

  1. A.acquire, serve, retain and advocate
  2. B.receiving, put-away, picking and packing
  3. C.planning, optimisation, execution and settlement
  4. D.sourcing, procurement, performance and payment
Answer: C
planning, optimisation, execution and settlement

planning, optimisation, execution and settlement. Plan, optimise, execute, settle.

Source: answer explanations, p. 72
QUESTION 112R · PDF p. 33

Freight audit and carrier invoice reconciliation belong to which TMS function?

  1. A.Planning
  2. B.Optimisation
  3. C.Settlement
  4. D.Execution
Answer: C
Settlement

Settlement. Settlement closes the financial side of each shipment.

Source: answer explanations, p. 72
QUESTION 113Ap · PDF p. 33

An urgent, high-value electronic component must reach a factory abroad within 24 hours. Which mode should the TMS recommend?

  1. A.Air
  2. B.Rail
  3. C.Inland waterway
  4. D.Sea
Answer: A
Air

Air. Air is fastest and suits urgent, high-value cargo.

Source: answer explanations, p. 72
QUESTION 114Ap · PDF p. 33

A shipper moves bulk commodities from Vietnam to Europe and seeks the lowest cost per unit with no urgency. Which mode is most suitable?

  1. A.Sea
  2. B.Express courier
  3. C.Road only
  4. D.Air
Answer: A
Sea

Sea. Sea is cheapest per unit but slowest.

Source: answer explanations, p. 72
QUESTION 115U · PDF p. 33

Which set lists constraints a vehicle routing solution must balance?

  1. A.Customer lifetime value and churn
  2. B.Vehicle capacity, customer time windows, driver hours, traffic and order priority
  3. C.Supplier score, invoice date and tax code
  4. D.Shelf height, pallet colour and barcode type
Answer: B
Vehicle capacity, customer time windows, driver hours, traffic and order priority

Vehicle capacity, customer time windows, driver hours, traffic and order priority. These operational constraints define a feasible route.

Source: answer explanations, p. 73
QUESTION 116R · PDF p. 33

According to the lecture, what is the typical saving from route optimisation?

  1. A.10–30% of distance and cost
  2. B.1–2%
  3. C.60–80%
  4. D.No measurable saving
Answer: A
10–30% of distance and cost

10–30% of distance and cost. This is prescriptive analytics in action.

Source: answer explanations, p. 73
QUESTION 117U · PDF p. 34

What is the main benefit of integrating WMS and TMS at the dock?

  1. A.No need for drivers
  2. B.Less dock waiting, higher vehicle utilisation and more accurate delivery estimates
  3. C.Elimination of all picking errors
  4. D.Lower supplier prices
Answer: B
Less dock waiting, higher vehicle utilisation and more accurate delivery estimates

Less dock waiting, higher vehicle utilisation and more accurate delivery estimates. The truck is scheduled to arrive when the load is ready.

Source: answer explanations, p. 73
QUESTION 118R · PDF p. 34

Which system manages gates, docks and yard moves?

  1. A.Yard management system (YMS)
  2. B.Customer relationship management (CRM)
  3. C.Labour management system (LMS)
  4. D.Global trade management (GTM)
Answer: A
Yard management system (YMS)

Yard management system (YMS). YMS covers the yard; GTM covers customs and trade compliance.

Source: answer explanations, p. 73
QUESTION 119U · PDF p. 34

What is the main limitation of the nearest-neighbour routing heuristic?

  1. A.It always produces the longest route
  2. B.It is fast and simple but does not guarantee the optimal route
  3. C.It ignores the depot
  4. D.It cannot be computed by hand
Answer: B
It is fast and simple but does not guarantee the optimal route

It is fast and simple but does not guarantee the optimal route. Greedy choices can be improved, e.g. by swapping stops.

Source: answer explanations, p. 73
QUESTION 120An · PDF p. 34

Comparing Ocado (robotic fulfilment) and Abivin vRoute (algorithmic routing), which statement is most accurate?

  1. A.Algorithmic optimisation needs low capital and deploys quickly; robotic automation needs heavy capital but transforms throughput, so risk profiles differ
  2. B.Both require identical investment and risk
  3. C.Routing algorithms only work in the UK
  4. D.Robotics needs no software
Answer: A
Algorithmic optimisation needs low capital and deploys quickly; robotic automation needs heavy capital but transforms throughput, so risk profiles differ

Algorithmic optimisation needs low capital and deploys quickly; robotic automation needs heavy capital but transforms throughput, so risk profiles differ. Hardware and algorithms differ in cost, speed of deployment and reversibility.

Source: answer explanations, p. 73
SESSION 07 / 15

Data-capture technology

Questions 121–140 · 20 questions

QUESTION 121U · PDF p. 34

“Garbage in, garbage out” means that…

  1. A.waste should be recycled in warehouses
  2. B.wrong input makes every downstream analysis, report and decision wrong, however advanced the system
  3. C.old data must be deleted regularly
  4. D.advanced systems automatically correct any input
Answer: B
wrong input makes every downstream analysis, report and decision wrong, however advanced the system

wrong input makes every downstream analysis, report and decision wrong, however advanced the system. This is why capture quality justifies investment.

Source: answer explanations, p. 73
QUESTION 122R · PDF p. 34

According to the lecture, the typical error rate of manual entry is about…

  1. A.1 per million fields
  2. B.0%
  3. C.25% per field
  4. D.1% per field
Answer: D
1% per field

1% per field. Automated capture reduces errors to roughly one per million reads.

Source: answer explanations, p. 73
QUESTION 123R · PDF p. 35

A 1D barcode typically holds about…

  1. A.a full PDF document
  2. B.10–20 characters
  3. C.several thousand characters
  4. D.an image of the product
Answer: B
10–20 characters

10–20 characters. Low capacity is the main limitation of linear barcodes.

Source: answer explanations, p. 73
QUESTION 124U · PDF p. 35

Compared with a 1D barcode, a 2D QR code…

  1. A.holds much more data, reads from any angle and includes error correction
  2. B.holds less data and needs radio waves
  3. C.cannot be scanned by a phone
  4. D.requires a battery
Answer: A
holds much more data, reads from any angle and includes error correction

holds much more data, reads from any angle and includes error correction. Two axes and error correction give capacity and robustness.

Source: answer explanations, p. 73
QUESTION 125R · PDF p. 35

In GS1 standards, the GTIN identifies…

  1. A.a truck driver
  2. B.a product type (trade item)
  3. C.one specific pallet
  4. D.a warehouse location
Answer: B
a product type (trade item)

a product type (trade item). The GTIN is the number under the retail barcode.

Source: answer explanations, p. 73
QUESTION 126R · PDF p. 35

Which GS1 code identifies one specific pallet or carton (a logistic unit)?

  1. A.GTIN
  2. B.SSCC
  3. C.EAN prefix 893
  4. D.GLN
Answer: B
SSCC

SSCC. SSCC is serialised, so each unit is unique.

Source: answer explanations, p. 73
QUESTION 127R · PDF p. 35

Which GS1 code identifies a place or legal entity and is used in EDI to state where to deliver?

  1. A.SSCC
  2. B.QR
  3. C.GLN
  4. D.GTIN
Answer: C
GLN

GLN. GLN = Global Location Number.

Source: answer explanations, p. 73
QUESTION 128R · PDF p. 35

The GS1 country prefix for Vietnam is…

  1. A.840
  2. B.400
  3. C.893
  4. D.690
Answer: C
893

893. GS1 Vietnam issues company prefixes beginning with 893.

Source: answer explanations, p. 73
QUESTION 129R · PDF p. 35

On a GS1-128 pallet label, the Application Identifier (17) denotes…

  1. A.the batch or lot number
  2. B.the SSCC
  3. C.the expiry date
  4. D.the GTIN
Answer: C
the expiry date

the expiry date. (00) SSCC, (01) GTIN, (10) batch, (17) expiry.

Source: answer explanations, p. 73
QUESTION 130U · PDF p. 36

Which statement correctly compares passive and active RFID tags?

  1. A.Active tags need line of sight
  2. B.Passive tags are more expensive and have longer range
  3. C.Passive tags have no battery and are powered by the reader; active tags have a battery and a much longer range
  4. D.Both require a printed barcode to work
Answer: C
Passive tags have no battery and are powered by the reader; active tags have a battery and a much longer range

Passive tags have no battery and are powered by the reader; active tags have a battery and a much longer range. Power source determines cost and range.

Source: answer explanations, p. 73
QUESTION 131U · PDF p. 36

RFID’s defining advantage over barcodes is…

  1. A.reading many tags at once without line of sight
  2. B.lower cost per unit
  3. C.greater data capacity than QR in all cases
  4. D.no need for any reader
Answer: A
reading many tags at once without line of sight

reading many tags at once without line of sight. Bulk, non-line-of-sight reading suits pallets and gates.

Source: answer explanations, p. 73
QUESTION 132Ap · PDF p. 36

A warehouse must inventory an entire pallet of mixed cartons in minutes as it passes through a gate. Which technology fits best?

  1. A.1D barcode
  2. B.Manual tally sheet
  3. C.OCR of handwritten notes
  4. D.RFID
Answer: D
RFID

RFID. Bulk reading at the gate counts everything at once.

Source: answer explanations, p. 73
QUESTION 133Ap · PDF p. 36

A vaccine truck must keep 2–8 °C throughout the journey with instant alerts. Which technology is required?

  1. A.IoT temperature sensors with GPS reporting to a monitoring platform
  2. B.A printed packing list
  3. C.A 1D barcode on each box
  4. D.EDI invoices
Answer: A
IoT temperature sensors with GPS reporting to a monitoring platform

IoT temperature sensors with GPS reporting to a monitoring platform. Continuous condition monitoring is the role of IoT sensors.

Source: answer explanations, p. 73
QUESTION 134Ap · PDF p. 36

RFID tags cost 10,000 VND each and a firm ships 100,000 cartons per year. What is the annual tag cost?

  1. A.100 million VND
  2. B.1 billion VND
  3. C.10 billion VND
  4. D.10 million VND
Answer: B
1 billion VND

1 billion VND. 10,000 × 100,000 = 1,000,000,000 VND; it is justified only for high-value or high-velocity goods.

Source: answer explanations, p. 73
QUESTION 135Ap · PDF p. 36

A scanner project costs 450 million VND and yields a net benefit of 24 million VND per month. What is the approximate payback period?

  1. A.About 45 months
  2. B.About 24 months
  3. C.About 19 months
  4. D.About 9 months
Answer: C
About 19 months

About 19 months. 450 ÷ 24 ≈ 18.75 months, within the Vietnamese norm of under 24 months.

Source: answer explanations, p. 73
QUESTION 136U · PDF p. 37

Which practice allows duplicate scans of the same carton to be detected automatically?

  1. A.Labelling each logistic unit with a serialised SSCC
  2. B.Using the same GTIN on all cartons
  3. C.Scanning before the goods are loaded
  4. D.Typing codes manually
Answer: A
Labelling each logistic unit with a serialised SSCC

Labelling each logistic unit with a serialised SSCC. A serial code is unique, so a second scan is recognised.

Source: answer explanations, p. 73
QUESTION 137U · PDF p. 37

When should a “loaded” scan be performed to avoid “right scan, wrong moment” errors?

  1. A.At the completion of the physical action, when the carton is actually loaded
  2. B.At month end
  3. C.Before picking starts
  4. D.When the order is created
Answer: A
At the completion of the physical action, when the carton is actually loaded

At the completion of the physical action, when the carton is actually loaded. Scanning early records events that may not happen.

Source: answer explanations, p. 74
QUESTION 138R · PDF p. 37

Which item is NOT typically captured by vehicle telematics?

  1. A.Live location and route
  2. B.Fuel level and consumption
  3. C.The customer’s credit limit
  4. D.Idle and stop times
Answer: C
The customer’s credit limit

The customer’s credit limit. Credit limits are partner master data in ERP.

Source: answer explanations, p. 74
QUESTION 139U · PDF p. 37

Which flow describes a typical IoT monitoring architecture?

  1. A.Sensor → IoT gateway → cloud → alert and dashboard
  2. B.Cloud → barcode → printer → sensor
  3. C.Dashboard → sensor → invoice → gateway
  4. D.ERP → sensor → driver → gateway
Answer: A
Sensor → IoT gateway → cloud → alert and dashboard

Sensor → IoT gateway → cloud → alert and dashboard. Data move from the edge to the cloud and then to people who act.

Source: answer explanations, p. 74
QUESTION 140An · PDF p. 37

A firm proposes buying drones and AGVs although it still records receipts on paper. Which advice is most consistent with the lecture?

  1. A.Buy the drones first and define the process afterwards
  2. B.Choose devices by brand popularity
  3. C.Define the process and build the barcode/QR foundation first; automate later once data capture is reliable
  4. D.Skip barcodes because computer vision is newer
Answer: C
Define the process and build the barcode/QR foundation first; automate later once data capture is reliable

Define the process and build the barcode/QR foundation first; automate later once data capture is reliable. Firms that buy hardware first end up with hardware in a cupboard.

Source: answer explanations, p. 74
SESSION 08 / 15

Midterm review

Questions 141–160 · 20 questions

QUESTION 141Ap · PDF p. 37

Four components of a perfect order (on time, in full, undamaged, correct documents) are each achieved 95% of the time independently. What is the perfect order rate?

  1. A.About 90%
  2. B.About 76%
  3. C.95%
  4. D.About 81.5%
Answer: D
About 81.5%

About 81.5%. 0.95⁴ ≈ 0.8145; it is a product, not an average.

Source: answer explanations, p. 74
QUESTION 142U · PDF p. 38

Which cross-session chain is described in the review?

  1. A.Migration is unrelated to data capture
  2. B.Better hardware always fixes process problems
  3. C.Reports create data quality automatically
  4. D.Dirty data starts at capture, wrecks the migration and then corrupts every report
Answer: D
Dirty data starts at capture, wrecks the migration and then corrupts every report

Dirty data starts at capture, wrecks the migration and then corrupts every report. Sessions 3, 7 and 11 describe the same data-quality thread.

Source: answer explanations, p. 74
QUESTION 143U · PDF p. 38

Integration inside one firm and integration between firms are addressed respectively by…

  1. A.ERP; EDI/API
  2. B.EDI; ERP
  3. C.CRM; WMS
  4. D.RFID; GPS
Answer: A
ERP; EDI/API

ERP; EDI/API. Same problem, two scopes.

Source: answer explanations, p. 74
QUESTION 144Ap · PDF p. 38

A distributor has three warehouses, no in-house IT team and must improve stock accuracy within six months. Which recommendation follows the strong-answer pattern?

  1. A.Build a custom WMS with a new four-person team
  2. B.SaaS WMS, piloted at the highest-volume warehouse for two months, then phased; full stock count before migration as the main risk control
  3. C.Switch all three warehouses at once with no data cleansing
  4. D.“They should implement a WMS to manage the warehouse better.”
Answer: B
SaaS WMS, piloted at the highest-volume warehouse for two months, then phased; full stock count before migration as the main risk control

SaaS WMS, piloted at the highest-volume warehouse for two months, then phased; full stock count before migration as the main risk control. A strong answer is argued from the case facts, with conditions and the largest risk.

Source: answer explanations, p. 74
QUESTION 145Ap · PDF p. 38

In the five-step case method, which statement names the problem rather than a symptom?

  1. A.Deliveries are late
  2. B.Customers are complaining
  3. C.Phones ring constantly
  4. D.The firm has no real-time visibility of shipment status
Answer: D
The firm has no real-time visibility of shipment status

The firm has no real-time visibility of shipment status. Late delivery is a symptom; lack of visibility is the problem.

Source: answer explanations, p. 74
QUESTION 146U · PDF p. 38

Which statement correctly distinguishes TCO from ROI?

  1. A.ROI is the licence fee; TCO is the training fee
  2. B.TCO is a security metric
  3. C.TCO is the total money spent over the system’s life; ROI is the net benefit relative to the investment
  4. D.TCO and ROI both measure revenue
Answer: C
TCO is the total money spent over the system’s life; ROI is the net benefit relative to the investment

TCO is the total money spent over the system’s life; ROI is the net benefit relative to the investment. One measures cost, the other return.

Source: answer explanations, p. 74
QUESTION 147Ap · PDF p. 38

Receiving staff scan one label to accept a whole pallet against the supplier’s despatch advice. Which code makes this possible?

  1. A.An internal invoice number
  2. B.GLN
  3. C.SSCC
  4. D.GTIN
Answer: C
SSCC

SSCC. The SSCC links the physical unit to its electronic contents.

Source: answer explanations, p. 74
QUESTION 148Ap · PDF p. 39

A firm wants to know where its trucks are and reroute them around traffic in real time. Which combination is required?

  1. A.SRM scorecards
  2. B.TMS fed by GPS/telematics
  3. C.Analytical CRM
  4. D.WMS with slotting
Answer: B
TMS fed by GPS/telematics

TMS fed by GPS/telematics. Live position data power TMS re-planning.

Source: answer explanations, p. 74
QUESTION 149U · PDF p. 39

Which pairing is INCORRECT?

  1. A.ESS – strategic dashboards for executives
  2. B.SaaS – the customer manages only its data
  3. C.TPS – daily operational transactions
  4. D.OLAP – recording a single order in real time
Answer: D
OLAP – recording a single order in real time

OLAP – recording a single order in real time. Recording a single order is OLTP.

Source: answer explanations, p. 74
QUESTION 150Ap · PDF p. 39

If inventory quantities in the ERP are wrong, what breaks downstream?

  1. A.Order promising, replenishment, picking, financial valuation and KPIs all become unreliable
  2. B.Only the warehouse colour coding
  3. C.Nothing, because ERP corrects itself
  4. D.Only the HR module
Answer: A
Order promising, replenishment, picking, financial valuation and KPIs all become unreliable

Order promising, replenishment, picking, financial valuation and KPIs all become unreliable. A shared database propagates errors as efficiently as it propagates truth.

Source: answer explanations, p. 74
QUESTION 151U · PDF p. 39

Many ERP failures can be explained by which Session 1 concept?

  1. A.The DIKW pyramid alone
  2. B.The five Vs
  3. C.The five-component model: software is only one of five, and people and process decide success
  4. D.The CIA triad
Answer: C
The five-component model: software is only one of five, and people and process decide success

The five-component model: software is only one of five, and people and process decide success. S1 → S4 link from the revision slides.

Source: answer explanations, p. 74
QUESTION 152Ap · PDF p. 39

“Warehouse A holds 47 cartons at month end every month, so order less there next month.” This statement corresponds to which DIKW level?

  1. A.Knowledge only
  2. B.Wisdom
  3. C.Data
  4. D.Information
Answer: B
Wisdom

Wisdom. It turns a known pattern into a judgement about action.

Source: answer explanations, p. 74
QUESTION 153Ap · PDF p. 39

Low-value bulk goods moved in a stable process need item identification at receipt and dispatch. Which capture technology is most appropriate?

  1. A.Drones
  2. B.Barcode
  3. C.IoT temperature sensors
  4. D.Active RFID on every unit
Answer: B
Barcode

Barcode. Choose by goods value, data granularity and environment, not novelty.

Source: answer explanations, p. 74
QUESTION 154U · PDF p. 40

What is the clearest distinction between WMS and TMS?

  1. A.WMS manages customers; TMS manages suppliers
  2. B.WMS operates inside the four walls of the warehouse; TMS operates out on the road
  3. C.They are identical systems
  4. D.WMS is cloud-only; TMS is on-premise only
Answer: B
WMS operates inside the four walls of the warehouse; TMS operates out on the road

WMS operates inside the four walls of the warehouse; TMS operates out on the road. The most common exam question: inside versus on the road.

Source: answer explanations, p. 74
QUESTION 155U · PDF p. 40

Around ERP, satellite systems such as WMS, TMS and CRM usually integrate on which data?

  1. A.Network cable lengths
  2. B.Inventory and order data
  3. C.Screen colour settings
  4. D.Employee birthdays
Answer: B
Inventory and order data

Inventory and order data. Orders and stock are the shared backbone.

Source: answer explanations, p. 74
QUESTION 156Ap · PDF p. 40

A dispatcher edits the delivered quantity of a shipment without authorisation. Which CIA objective is breached?

  1. A.Confidentiality
  2. B.Velocity
  3. C.Availability
  4. D.Integrity
Answer: D
Integrity

Integrity. Unauthorised modification breaches integrity – a most-missed item.

Source: answer explanations, p. 74
QUESTION 157Ap · PDF p. 40

“You manage only your data; the provider runs everything else.” Which cloud level is this?

  1. A.SaaS
  2. B.On-premise
  3. C.IaaS
  4. D.PaaS
Answer: A
SaaS

SaaS. SaaS leaves only data and users to the customer.

Source: answer explanations, p. 74
QUESTION 158U · PDF p. 40

For an essay asking for “two risks” of an Excel-to-WMS migration, what earns full credit according to the review guidance?

  1. A.Listing as many risks as possible without explanation
  2. B.Retelling the scenario in detail
  3. C.Each risk is paired with a matched mitigation and tied to the firm’s situation
  4. D.Naming software brands only
Answer: C
Each risk is paired with a matched mitigation and tied to the firm’s situation

Each risk is paired with a matched mitigation and tied to the firm’s situation. A bare risk earns half marks.

Source: answer explanations, p. 74
QUESTION 159An · PDF p. 40

Which statement explains a benefit of WMS together with its mechanism?

  1. A.A WMS has a better interface
  2. B.Stock accuracy improves because each movement is recorded by scan at the moment it happens
  3. C.A WMS is more modern than Excel
  4. D.Many large firms use a WMS
Answer: B
Stock accuracy improves because each movement is recorded by scan at the moment it happens

Stock accuracy improves because each movement is recorded by scan at the moment it happens. Markers look for the mechanism, not a slogan.

Source: answer explanations, p. 74
QUESTION 160Ap · PDF p. 41

5,000 units were ordered and 4,900 delivered. What is the fill rate?

  1. A.2%
  2. B.102%
  3. C.98%
  4. D.49%
Answer: C
98%

98%. 4,900 ÷ 5,000 = 98%; fill rate measures completeness, not timing.

Source: answer explanations, p. 75
SESSION 09 / 15

Business processes and modelling

Questions 161–180 · 20 questions

QUESTION 161R · PDF p. 41

A business process is best defined as…

  1. A.a structured set of activities that transforms inputs into outputs of value to a customer
  2. B.a software module in an ERP
  3. C.a list of employees
  4. D.an organisational chart
Answer: A
a structured set of activities that transforms inputs into outputs of value to a customer

a structured set of activities that transforms inputs into outputs of value to a customer. Inputs, activities, roles and outputs define a process.

Source: answer explanations, p. 75
QUESTION 162Ap · PDF p. 41

IT maintenance, HR and finance in a logistics firm are examples of which process type?

  1. A.Support processes
  2. B.Core processes
  3. C.Customer processes
  4. D.Management processes
Answer: A
Support processes

Support processes. They enable the core processes to run.

Source: answer explanations, p. 75
QUESTION 163U · PDF p. 41

Which metric captures how long the customer actually waits?

  1. A.Lead time
  2. B.Error rate
  3. C.Space utilisation
  4. D.Cost per transaction
Answer: A
Lead time

Lead time. Cycle time is internal start-to-finish; lead time is the customer’s wait.

Source: answer explanations, p. 75
QUESTION 164R · PDF p. 41

The minimum input for process mining is an event log with which three columns?

  1. A.Supplier, weight, colour
  2. B.Case ID, activity, timestamp
  3. C.Driver, route, fuel
  4. D.Customer name, price, discount
Answer: B
Case ID, activity, timestamp

Case ID, activity, timestamp. ERP and WMS usually already log these.

Source: answer explanations, p. 75
QUESTION 165U · PDF p. 41

What is the key limitation of process mining?

  1. A.It requires interviews with every employee
  2. B.It sees only what systems record, so phone calls and spreadsheet work must be captured by observation
  3. C.It cannot measure waiting time
  4. D.It works only on paper documents
Answer: B
It sees only what systems record, so phone calls and spreadsheet work must be captured by observation

It sees only what systems record, so phone calls and spreadsheet work must be captured by observation. Combine it with observation rather than replace observation.

Source: answer explanations, p. 75
QUESTION 166R · PDF p. 42

In a flowchart, a diamond represents…

  1. A.a decision with two or more labelled exits
  2. B.data input or output
  3. C.an activity
  4. D.the start or end
Answer: A
a decision with two or more labelled exits

a decision with two or more labelled exits. Every decision needs labelled branches that all resolve.

Source: answer explanations, p. 75
QUESTION 167R · PDF p. 42

Which is NOT a to-be design principle presented in the lecture?

  1. A.Add an approval step to every transaction
  2. B.Automate the rule-based work
  3. C.Parallelise independent work
  4. D.Eliminate non-value steps
Answer: A
Add an approval step to every transaction

Add an approval step to every transaction. Extra approvals add waiting and hand-offs.

Source: answer explanations, p. 75
QUESTION 168U · PDF p. 42

In BPMN, how do XOR and AND gateways differ?

  1. A.XOR is for start events; AND for end events
  2. B.There is no difference
  3. C.XOR takes exactly one path; AND takes all paths in parallel
  4. D.XOR shows data; AND shows people
Answer: C
XOR takes exactly one path; AND takes all paths in parallel

XOR takes exactly one path; AND takes all paths in parallel. Gateways control branching and merging.

Source: answer explanations, p. 75
QUESTION 169U · PDF p. 42

In BPMN, a dashed connector between two pools represents…

  1. A.a message flow between parties
  2. B.the sequence of tasks within one party
  3. C.a decision
  4. D.a data store
Answer: A
a message flow between parties

a message flow between parties. Solid lines are sequence flows; dashed lines are messages.

Source: answer explanations, p. 75
QUESTION 170R · PDF p. 42

SIPOC stands for…

  1. A.Systems, Integration, Performance, Operations, Control
  2. B.Scope, Issues, Plan, Owner, Cost
  3. C.Sales, Inventory, Procurement, Orders, Cash
  4. D.Suppliers, Inputs, Process, Outputs, Customers
Answer: D
Suppliers, Inputs, Process, Outputs, Customers

Suppliers, Inputs, Process, Outputs, Customers. SIPOC scopes a process on one page.

Source: answer explanations, p. 75
QUESTION 171U · PDF p. 42

When filling the Process column of a SIPOC, finding more than seven steps indicates that…

  1. A.the scope is too wide and should be split
  2. B.the customer column can be omitted
  3. C.automation is mandatory
  4. D.the process is perfectly designed
Answer: A
the scope is too wide and should be split

the scope is too wide and should be split. SIPOC is a high-level scoping tool.

Source: answer explanations, p. 75
QUESTION 172U · PDF p. 42

Why is a swimlane diagram more useful than a plain flowchart for a multi-department process?

  1. A.It uses more colours
  2. B.It shows only IT systems
  3. C.It removes the need for decisions
  4. D.It assigns each step to a participant, so hand-offs – points of waiting, lost information and error – become visible
Answer: D
It assigns each step to a participant, so hand-offs – points of waiting, lost information and error – become visible

It assigns each step to a participant, so hand-offs – points of waiting, lost information and error – become visible. A flowchart shows sequence but not responsibility.

Source: answer explanations, p. 75
QUESTION 173R · PDF p. 43

A bottleneck is the process step with…

  1. A.the highest cost
  2. B.the lowest capacity
  3. C.the most staff
  4. D.the newest software
Answer: B
the lowest capacity

the lowest capacity. The slowest step governs throughput.

Source: answer explanations, p. 75
QUESTION 174Ap · PDF p. 43

Receiving handles 120 pallets/hour, inspection 60/hour and put-away 90/hour. What is the process throughput and where is the bottleneck?

  1. A.120 pallets/hour; receiving
  2. B.90 pallets/hour; put-away
  3. C.270 pallets/hour; no bottleneck
  4. D.60 pallets/hour; inspection
Answer: D
60 pallets/hour; inspection

60 pallets/hour; inspection. Throughput equals the minimum capacity in the chain.

Source: answer explanations, p. 75
QUESTION 175U · PDF p. 43

Why does improving a non-bottleneck step barely help?

  1. A.Non-bottleneck steps have no cost
  2. B.Customers only see the first step
  3. C.Bottlenecks disappear automatically
  4. D.Overall throughput is still limited by the bottleneck
Answer: D
Overall throughput is still limited by the bottleneck

Overall throughput is still limited by the bottleneck. This is the most common improvement-project error.

Source: answer explanations, p. 75
QUESTION 176R · PDF p. 43

Which is NOT one of the seven lean wastes listed in the lecture?

  1. A.Waiting
  2. B.Duplicate data entry
  3. C.Over-processing
  4. D.Value-adding work requested by the customer
Answer: D
Value-adding work requested by the customer

Value-adding work requested by the customer. Waste is activity that adds cost without customer value.

Source: answer explanations, p. 75
QUESTION 177Ap · PDF p. 43

In the 5 Whys example (late delivery → truck left late → goods not packed → pick list printed late → waiting for credit confirmation), what is the root cause?

  1. A.The truck is too slow
  2. B.The driver left too late
  3. C.Credit limits are not checked automatically at order creation
  4. D.The packers are careless
Answer: C
Credit limits are not checked automatically at order creation

Credit limits are not checked automatically at order creation. The symptom is in transport; the cause is in finance.

Source: answer explanations, p. 75
QUESTION 178R · PDF p. 43

Which category is NOT among the six fishbone categories used in the lecture?

  1. A.Data
  2. B.Marketing
  3. C.Environment
  4. D.People
Answer: B
Marketing

Marketing. People, process, system, equipment, data, environment.

Source: answer explanations, p. 75
QUESTION 179U · PDF p. 43

How should the as-is process be drawn?

  1. A.From the target design
  2. B.From the vendor’s brochure
  3. C.From observed reality and evidence, not from the written policy
  4. D.From management’s assumptions only
Answer: C
From observed reality and evidence, not from the written policy

From observed reality and evidence, not from the written policy. Policy and practice usually differ.

Source: answer explanations, p. 75
QUESTION 180An · PDF p. 44

A firm wants RPA to copy emailed orders into the ERP, but 30% of emails need judgement and the process has three redundant approvals. What is the best advice?

  1. A.Redesign the process first (remove redundant approvals, standardise inputs), then automate only the structured, rule-based portion
  2. B.Abandon the ERP
  3. C.Automate everything immediately, including judgement cases
  4. D.Add a fourth approval to control the robot
Answer: A
Redesign the process first (remove redundant approvals, standardise inputs), then automate only the structured, rule-based portion

Redesign the process first (remove redundant approvals, standardise inputs), then automate only the structured, rule-based portion. Automating a bad process only makes it run faster.

Source: answer explanations, p. 75
SESSION 10 / 15

SDLC and requirements engineering

Questions 181–200 · 20 questions

QUESTION 181R · PDF p. 44

Which sequence gives the six SDLC phases?

  1. A.Planning → Design → Deployment → Analysis → Implementation → Maintenance
  2. B.Analysis → Planning → Deployment → Design → Maintenance → Implementation
  3. C.Design → Implementation → Planning → Analysis → Maintenance → Deployment
  4. D.Planning → Analysis → Design → Implementation → Deployment → Maintenance
Answer: D
Planning → Analysis → Design → Implementation → Deployment → Maintenance

Planning → Analysis → Design → Implementation → Deployment → Maintenance. Each phase answers one question before the next begins.

Source: answer explanations, p. 76
QUESTION 182U · PDF p. 44

Which SDLC phase determines what the system must do?

  1. A.Planning
  2. B.Deployment
  3. C.Design
  4. D.Analysis
Answer: D
Analysis

Analysis. Analysis produces the requirements.

Source: answer explanations, p. 76
QUESTION 183U · PDF p. 44

Why is time spent in the analysis phase highly cost-effective?

  1. A.Analysis requires no users
  2. B.Analysis replaces testing
  3. C.Maintenance costs nothing
  4. D.An error caught in analysis is nearly free, whereas the same error found after go-live can cost up to about a hundred times more
Answer: D
An error caught in analysis is nearly free, whereas the same error found after go-live can cost up to about a hundred times more

An error caught in analysis is nearly free, whereas the same error found after go-live can cost up to about a hundred times more. Fix costs rise sharply by phase.

Source: answer explanations, p. 76
QUESTION 184R · PDF p. 44

TELOS stands for…

  1. A.Testing, Engineering, Logistics, Operations, Security
  2. B.Time, Effort, Labour, Output, Scope
  3. C.Technology, Ethics, Law, Organisation, Strategy
  4. D.Technical, Economic, Legal, Operational, Schedule
Answer: D
Technical, Economic, Legal, Operational, Schedule

Technical, Economic, Legal, Operational, Schedule. Five dimensions of feasibility.

Source: answer explanations, p. 76
QUESTION 185Ap · PDF p. 44

Checking compliance with the e-invoice decree, the cybersecurity law and data-retention rules belongs to which feasibility dimension?

  1. A.Technical
  2. B.Schedule
  3. C.Operational
  4. D.Legal
Answer: D
Legal

Legal. These are legal and regulatory constraints.

Source: answer explanations, p. 76
QUESTION 186Ap · PDF p. 45

A WMS costs 3 billion VND and saves 150 million VND per month. What is the payback period?

  1. A.20 months
  2. B.15 months
  3. C.45 months
  4. D.2 months
Answer: A
20 months

20 months. 3,000 ÷ 150 = 20 months, within the Vietnamese norm of under 24 months.

Source: answer explanations, p. 76
QUESTION 187Ap · PDF p. 45

An investment of 2 billion VND yields a net benefit of 1.5 billion VND. Using the lecture formula, what is the ROI?

  1. A.75%
  2. B.175%
  3. C.25%
  4. D.133%
Answer: A
75%

75%. ROI = net benefit ÷ investment × 100% = 1.5 ÷ 2 = 75%.

Source: answer explanations, p. 76
QUESTION 188U · PDF p. 45

A positive net present value (NPV) indicates that…

  1. A.the project has no risk
  2. B.discounted future cash flows exceed the investment, so the project is economically acceptable
  3. C.the payback period is under one month
  4. D.the project is technically feasible
Answer: B
discounted future cash flows exceed the investment, so the project is economically acceptable

discounted future cash flows exceed the investment, so the project is economically acceptable. Positive NPV means “go” on the economic criterion.

Source: answer explanations, p. 76
QUESTION 189Ap · PDF p. 45

“Waybill lookup returns in under 2 seconds at 500 concurrent users” is…

  1. A.a business process
  2. B.a user story without a role
  3. C.a non-functional (performance) requirement
  4. D.a functional requirement
Answer: C
a non-functional (performance) requirement

a non-functional (performance) requirement. It specifies how well, not what.

Source: answer explanations, p. 76
QUESTION 190Ap · PDF p. 45

“Raise an alert when stock falls below the reorder threshold” is…

  1. A.a cutover strategy
  2. B.a functional requirement
  3. C.a non-functional requirement
  4. D.a feasibility criterion
Answer: B
a functional requirement

a functional requirement. It describes behaviour the system must perform.

Source: answer explanations, p. 76
QUESTION 191U · PDF p. 45

Which is the best testable rewrite of “The system must be secure”?

  1. A.The system must be very secure
  2. B.Security will be decided later
  3. C.The system must use the best security
  4. D.Four defined roles; two-factor authentication for managers; an audit log on every inventory edit
Answer: D
Four defined roles; two-factor authentication for managers; an audit log on every inventory edit

Four defined roles; two-factor authentication for managers; an audit log on every inventory edit. A good requirement carries a number or an explicit list from which a test can be written.

Source: answer explanations, p. 76
QUESTION 192R · PDF p. 45

Which is the correct user story template?

  1. A.If [condition] then [action] else [error]
  2. B.The system shall be easy to use
  3. C.Given [price], when [discount], then [tax]
  4. D.As a [role], I want [goal], so that [benefit]
Answer: D
As a [role], I want [goal], so that [benefit]

As a [role], I want [goal], so that [benefit]. The story is completed by acceptance criteria.

Source: answer explanations, p. 76
QUESTION 193U · PDF p. 46

Which elicitation technique best reveals what people actually do rather than what they say they do?

  1. A.Questionnaire only
  2. B.Reading the vendor brochure
  3. C.Observation
  4. D.Executive interview only
Answer: C
Observation

Observation. Observation captures real practice; prototypes surface unspoken needs.

Source: answer explanations, p. 76
QUESTION 194U · PDF p. 46

In a use case diagram, the system boundary box mainly helps to…

  1. A.calculate the budget
  2. B.show the database schema
  3. C.list employees by name
  4. D.control scope creep: every new request must name an actor and sit inside the box
Answer: D
control scope creep: every new request must name an actor and sit inside the box

control scope creep: every new request must name an actor and sit inside the box. Actors are roles, not individuals, and may be external systems.

Source: answer explanations, p. 76
QUESTION 195R · PDF p. 46

In MoSCoW prioritisation, “W” means…

  1. A.Weekly requirement
  2. B.Won’t have this time – considered and deliberately deferred
  3. C.Will have immediately
  4. D.Wish list with no record
Answer: B
Won’t have this time – considered and deliberately deferred

Won’t have this time – considered and deliberately deferred. Won’t items are recorded, not forgotten.

Source: answer explanations, p. 76
QUESTION 196U · PDF p. 46

Why should Must-have items be limited to about 60% of a release’s effort?

  1. A.Because Must items are optional
  2. B.Because developers dislike Must items
  3. C.Because law limits Must items
  4. D.The remaining Should/Could items form a buffer that can be cut if the project slips, protecting the date and testing
Answer: D
The remaining Should/Could items form a buffer that can be cut if the project slips, protecting the date and testing

The remaining Should/Could items form a buffer that can be cut if the project slips, protecting the date and testing. If everything is Must, nothing can be cut.

Source: answer explanations, p. 76
QUESTION 197Ap · PDF p. 46

Requirements are stable, regulation-driven and changing direction would be very costly. Which delivery model fits best?

  1. A.No methodology
  2. B.Big-bang coding without analysis
  3. C.Waterfall (or a plan-driven hybrid)
  4. D.Pure Agile with no upfront plan
Answer: C
Waterfall (or a plan-driven hybrid)

Waterfall (or a plan-driven hybrid). Stable requirements and high change cost favour Waterfall.

Source: answer explanations, p. 76
QUESTION 198Ap · PDF p. 46

A backlog totals 240 story points and the team’s stable velocity is 30 points per two-week sprint. What is the expected duration?

  1. A.8 sprints, about 4 months
  2. B.16 sprints, about 8 months
  3. C.4 sprints, about 2 months
  4. D.30 sprints, about 15 months
Answer: A
8 sprints, about 4 months

8 sprints, about 4 months. 240 ÷ 30 = 8 sprints × 2 weeks = 16 weeks ≈ 4 months.

Source: answer explanations, p. 76
QUESTION 199U · PDF p. 47

Custom development (build) is most justified when…

  1. A.the firm has no IT team
  2. B.the budget is small and time is short
  3. C.the need is industry-standard
  4. D.the process is a genuine competitive advantage and in-house capability exists
Answer: D
the process is a genuine competitive advantage and in-house capability exists

the process is a genuine competitive advantage and in-house capability exists. Build only your differentiator; buy or rent the rest.

Source: answer explanations, p. 76
QUESTION 200An · PDF p. 47

A 3PL with 300 staff and no development capability has six weeks to provide shipment tracking or lose its biggest customer. Why is a domestic modular SaaS the best choice?

  1. A.Custom development is always slower than one week
  2. B.International TMS packages are illegal in Vietnam
  3. C.SaaS always has the lowest total cost in every case
  4. D.The deadline decides; building is an unacceptable risk without capability; tracking is industry-standard rather than a differentiator
Answer: D
The deadline decides; building is an unacceptable risk without capability; tracking is industry-standard rather than a differentiator

The deadline decides; building is an unacceptable risk without capability; tracking is industry-standard rather than a differentiator. The choice is argued from time, capability and differentiation criteria.

Source: answer explanations, p. 76
SESSION 11 / 15

System deployment and change management

Questions 201–220 · 20 questions

QUESTION 201R · PDF p. 47

The four cutover strategies discussed are…

  1. A.waterfall, agile, hybrid and spiral
  2. B.big bang, phased, parallel and pilot
  3. C.unit, integration, UAT and performance
  4. D.avoid, mitigate, transfer and accept
Answer: B
big bang, phased, parallel and pilot

big bang, phased, parallel and pilot. Each trades speed against risk differently.

Source: answer explanations, p. 76
QUESTION 202U · PDF p. 47

Which statement best describes the big-bang strategy?

  1. A.Fastest and cheapest, but concentrates all risk at one moment
  2. B.Safest, because the old system remains as fallback
  3. C.Slowest, because sites switch one by one
  4. D.Risk-free if the vendor is large
Answer: A
Fastest and cheapest, but concentrates all risk at one moment

Fastest and cheapest, but concentrates all risk at one moment. A failure stops everything at once.

Source: answer explanations, p. 77
QUESTION 203U · PDF p. 47

Which cutover strategy is safest but most labour-intensive?

  1. A.Phased
  2. B.Parallel
  3. C.Pilot
  4. D.Big bang
Answer: B
Parallel

Parallel. Double entry gives a permanent fallback.

Source: answer explanations, p. 77
QUESTION 204Ap · PDF p. 47

A WMS will replace a legacy system in Hanoi (largest), Da Nang and Can Tho. Which approach is most defensible?

  1. A.Skip testing to save time
  2. B.Pilot at one site chosen by size and criticality, then phase the rollout to the others
  3. C.Big bang across all three sites in peak season
  4. D.Run parallel systems indefinitely in all sites
Answer: B
Pilot at one site chosen by size and criticality, then phase the rollout to the others

Pilot at one site chosen by size and criticality, then phase the rollout to the others. Pilot then phased limits risk and builds super-users.

Source: answer explanations, p. 77
QUESTION 205R · PDF p. 48

Which is NOT one of the four go/no-go conditions?

  1. A.Reconciliation is within tolerance
  2. B.Smoke tests have fully passed
  3. C.The vendor’s final invoice has been paid
  4. D.The rollback plan has been tested
Answer: C
The vendor’s final invoice has been paid

The vendor’s final invoice has been paid. The fourth condition is that support is fully staffed; all four are required.

Source: answer explanations, p. 77
QUESTION 206R · PDF p. 48

Which sequence gives the five data migration steps?

  1. A.Extract → cleanse → map → load → verify
  2. B.Load → extract → verify → map → cleanse
  3. C.Map → load → cleanse → extract → verify
  4. D.Verify → cleanse → extract → load → map
Answer: A
Extract → cleanse → map → load → verify

Extract → cleanse → map → load → verify. Cleansing is usually the longest step.

Source: answer explanations, p. 77
QUESTION 207U · PDF p. 48

In which direction should changes move across the three environments?

  1. A.Development → staging/UAT → production, one way only
  2. B.Randomly, depending on urgency
  3. C.Production → staging → development
  4. D.Directly in production because it is faster
Answer: A
Development → staging/UAT → production, one way only

Development → staging/UAT → production, one way only. Editing production directly is a common cause of serious outages.

Source: answer explanations, p. 77
QUESTION 208Ap · PDF p. 48

Which set of checks best verifies a data migration?

  1. A.Checking that the server is switched on
  2. B.Asking users whether the screens look nice
  3. C.Counting the number of modules
  4. D.Record counts, control totals and random samples compared between source and target
Answer: D
Record counts, control totals and random samples compared between source and target

Record counts, control totals and random samples compared between source and target. Quantitative reconciliation proves completeness and accuracy.

Source: answer explanations, p. 77
QUESTION 209Ap · PDF p. 48

Phone numbers in a supplier file have lost their leading zero. What is the most likely cause?

  1. A.The supplier changed its phone number
  2. B.The ERP encrypted the field
  3. C.RFID interference
  4. D.A spreadsheet treated the field as a number instead of text
Answer: D
A spreadsheet treated the field as a number instead of text

A spreadsheet treated the field as a number instead of text. This is one of six typical defects in Vietnamese logistics data.

Source: answer explanations, p. 77
QUESTION 210R · PDF p. 48

Which list gives the four test levels?

  1. A.Plan, do, check, act
  2. B.Unit, integration, user acceptance (UAT), performance
  3. C.Extract, transform, load, verify
  4. D.Awareness, desire, knowledge, ability
Answer: B
Unit, integration, user acceptance (UAT), performance

Unit, integration, user acceptance (UAT), performance. UAT is the decisive level for sign-off.

Source: answer explanations, p. 77
QUESTION 211U · PDF p. 48

Who should write and execute UAT scripts, and why?

  1. A.Nobody; UAT is optional
  2. B.The vendor’s sales team
  3. C.Developers only, because they wrote the code
  4. D.Business users, because only they know how the work really happens; UAT is the basis for sign-off
Answer: D
Business users, because only they know how the work really happens; UAT is the basis for sign-off

Business users, because only they know how the work really happens; UAT is the basis for sign-off. Real data (masked) and real scenarios expose real defects.

Source: answer explanations, p. 77
QUESTION 212U · PDF p. 49

According to the UAT rule in the lecture, for every happy-path script you should write…

  1. A.no additional scripts
  2. B.at least two exception scripts, because defects live in the exceptions
  3. C.a user story
  4. D.exactly one performance script
Answer: B
at least two exception scripts, because defects live in the exceptions

at least two exception scripts, because defects live in the exceptions. Short receipt, over-receipt and items not on the order are typical exceptions.

Source: answer explanations, p. 77
QUESTION 213R · PDF p. 49

ADKAR stands for…

  1. A.Assess, Develop, Kickoff, Adopt, Retire
  2. B.Awareness, Desire, Knowledge, Ability, Reinforcement
  3. C.Analysis, Design, Knowledge, Action, Review
  4. D.Accountable, Decide, Know, Approve, Report
Answer: B
Awareness, Desire, Knowledge, Ability, Reinforcement

Awareness, Desire, Knowledge, Ability, Reinforcement. Five sequential steps of individual change.

Source: answer explanations, p. 77
QUESTION 214Ap · PDF p. 49

Users understand the new system perfectly but still avoid using it. Which ADKAR element is missing?

  1. A.Knowledge
  2. B.Awareness
  3. C.Desire
  4. D.Ability
Answer: C
Desire

Desire. Understanding without willingness signals missing Desire.

Source: answer explanations, p. 77
QUESTION 215Ap · PDF p. 49

Staff used the system well for a month, then drifted back to Excel. Which ADKAR element is missing?

  1. A.Desire
  2. B.Awareness
  3. C.Knowledge
  4. D.Reinforcement
Answer: D
Reinforcement

Reinforcement. Measure adoption and close the old way to reinforce.

Source: answer explanations, p. 77
QUESTION 216U · PDF p. 49

Why is “add more training” often the wrong response to resistance?

  1. A.Training is always too expensive
  2. B.Training replaces UAT
  3. C.Users never need training
  4. D.Training only fixes Knowledge; resistance may come from missing Awareness, Desire or Reinforcement
Answer: D
Training only fixes Knowledge; resistance may come from missing Awareness, Desire or Reinforcement

Training only fixes Knowledge; resistance may come from missing Awareness, Desire or Reinforcement. Diagnose first, then apply the matched remedy.

Source: answer explanations, p. 77
QUESTION 217U · PDF p. 49

Hypercare refers to…

  1. A.a cloud service tier
  2. B.intensive on-site support during the first two to four weeks after go-live
  3. C.data cleansing
  4. D.load testing before go-live
Answer: B
intensive on-site support during the first two to four weeks after go-live

intensive on-site support during the first two to four weeks after go-live. Small frictions are resolved before they become reasons to abandon the system.

Source: answer explanations, p. 77
QUESTION 218R · PDF p. 49

In the three-tier support model, Tier 1 is usually provided by…

  1. A.the vendor
  2. B.the CEO
  3. C.local super-users
  4. D.internal IT developers
Answer: C
local super-users

local super-users. Tier 2 is internal IT; Tier 3 is the vendor for product defects.

Source: answer explanations, p. 77
QUESTION 219Ap · PDF p. 50

Warehouse operators have low power but high interest in a WMS project. Which stakeholder strategy applies?

  1. A.Keep satisfied
  2. B.Ignore until go-live
  3. C.Keep well informed – and recruit super-users from this group
  4. D.Monitor with minimal effort
Answer: C
Keep well informed – and recruit super-users from this group

Keep well informed – and recruit super-users from this group. Projects that ignore this quadrant are surprised by resistance on go-live day.

Source: answer explanations, p. 77
QUESTION 220An · PDF p. 50

What is the main lesson of Hershey’s 1999 implementation failure?

  1. A.Parallel running caused the failure
  2. B.Risk lay in timing and scope: ERP, CRM and SCM went live together, big bang, with compressed testing, just before peak season
  3. C.Hershey had too few customers
  4. D.The software was fundamentally defective
Answer: B
Risk lay in timing and scope: ERP, CRM and SCM went live together, big bang, with compressed testing, just before peak season

Risk lay in timing and scope: ERP, CRM and SCM went live together, big bang, with compressed testing, just before peak season. The failure was a deployment-decision failure, not a software failure.

Source: answer explanations, p. 77
SESSION 12 / 15

Logistics documents and data exchange

Questions 221–240 · 20 questions

QUESTION 221R · PDF p. 50

The three functions of a Bill of Lading are…

  1. A.receipt for the goods, evidence of the contract of carriage and document of title
  2. B.invoice, packing list and insurance
  3. C.booking, tracking and settlement
  4. D.certificate of origin, tax receipt and permit
Answer: A
receipt for the goods, evidence of the contract of carriage and document of title

receipt for the goods, evidence of the contract of carriage and document of title. Holding the original B/L gives the right to the cargo.

Source: answer explanations, p. 77
QUESTION 222U · PDF p. 50

The commercial invoice is mainly the basis for…

  1. A.transferring title to the goods
  2. B.scheduling the vessel
  3. C.proving the country of origin
  4. D.customs duty and payment, because it states the value of the goods
Answer: D
customs duty and payment, because it states the value of the goods

customs duty and payment, because it states the value of the goods. Title is transferred by the B/L, origin by the C/O.

Source: answer explanations, p. 77
QUESTION 223U · PDF p. 50

Why does the certificate of origin matter economically?

  1. A.It determines eligibility for preferential tariffs under free trade agreements
  2. B.It insures the cargo
  3. C.It replaces the customs declaration
  4. D.It sets the freight rate
Answer: A
It determines eligibility for preferential tariffs under free trade agreements

It determines eligibility for preferential tariffs under free trade agreements. Under EVFTA, for example, origin proof affects duty rates.

Source: answer explanations, p. 78
QUESTION 224R · PDF p. 50

Which document lists quantities, weights and dimensions per package and is used to check goods on receipt?

  1. A.Packing list
  2. B.Certificate of origin
  3. C.Insurance certificate
  4. D.Bill of Lading
Answer: A
Packing list

Packing list. The packing list must match the commercial invoice exactly.

Source: answer explanations, p. 78
QUESTION 225U · PDF p. 51

Under a letter of credit, why can a one-word difference in the goods description cause non-payment?

  1. A.The carrier decides payment
  2. B.Banks do not read documents
  3. C.The bank checks presented documents strictly against the L/C terms and refuses discrepant sets
  4. D.The buyer’s customs office pays
Answer: C
The bank checks presented documents strictly against the L/C terms and refuses discrepant sets

The bank checks presented documents strictly against the L/C terms and refuses discrepant sets. Document consistency is a data-quality problem with direct financial consequences.

Source: answer explanations, p. 78
QUESTION 226U · PDF p. 51

Under CIF (Incoterms 2020), which statement is correct?

  1. A.Risk and cost both transfer at the buyer’s door
  2. B.The seller pays freight and insurance to the destination port, but risk transfers at the export port
  3. C.The buyer pays all freight from the factory gate
  4. D.No insurance is involved
Answer: B
The seller pays freight and insurance to the destination port, but risk transfers at the export port

The seller pays freight and insurance to the destination port, but risk transfers at the export port. Cost and risk transfer at different places – the most commonly confused point.

Source: answer explanations, p. 78
QUESTION 227R · PDF p. 51

Under FOB, at which point does risk transfer from seller to buyer?

  1. A.When the goods are on board the vessel (the ship’s rail) at the export port
  2. B.At the buyer’s warehouse door
  3. C.At the seller’s factory gate
  4. D.At the destination port after discharge
Answer: A
When the goods are on board the vessel (the ship’s rail) at the export port

When the goods are on board the vessel (the ship’s rail) at the export port. FOB is the most common term for Vietnamese exports and needs no freight or insurance module on the seller side.

Source: answer explanations, p. 78
QUESTION 228Ap · PDF p. 51

A system must support DDP shipments. Which data requirement is heaviest?

  1. A.The supplier’s logo
  2. B.No freight data at all
  3. C.HS codes and the destination country’s tariff schedule
  4. D.Only the factory gate handover time
Answer: C
HS codes and the destination country’s tariff schedule

HS codes and the destination country’s tariff schedule. The seller bears duty to the buyer’s door, so tariff data are mandatory.

Source: answer explanations, p. 78
QUESTION 229R · PDF p. 51

EDI is best defined as…

  1. A.a shared spreadsheet on a USB drive
  2. B.the exchange of business documents between organisations as standard structured messages processed automatically, with no re-entry
  3. C.sending scanned PDFs by email
  4. D.a phone call between two clerks
Answer: B
the exchange of business documents between organisations as standard structured messages processed automatically, with no re-entry

the exchange of business documents between organisations as standard structured messages processed automatically, with no re-entry. A’s system sends a message; B’s system creates the record.

Source: answer explanations, p. 78
QUESTION 230R · PDF p. 51

Which EDI standard is the UN standard widely used in Europe and Asia?

  1. A.HTML
  2. B.ANSI X12
  3. C.JSON
  4. D.EDIFACT
Answer: D
EDIFACT

EDIFACT. ANSI X12 dominates North America.

Source: answer explanations, p. 78
QUESTION 231R · PDF p. 52

The EDIFACT message DESADV carries…

  1. A.a purchase order
  2. B.an invoice
  3. C.a shipment status update
  4. D.a despatch advice
Answer: D
a despatch advice

a despatch advice. ORDERS = order, INVOIC = invoice, IFTSTA = status.

Source: answer explanations, p. 78
QUESTION 232R · PDF p. 52

Which EDIFACT message is a transport instruction from shipper to carrier?

  1. A.IFTSTA
  2. B.ORDERS
  3. C.IFTMIN
  4. D.INVOIC
Answer: C
IFTMIN

IFTMIN. IFTMIN instructs; IFTSTA reports status.

Source: answer explanations, p. 78
QUESTION 233U · PDF p. 52

Why does EDI suit long-term partners only?

  1. A.EDI messages expire after one week
  2. B.EDI is illegal for short contracts
  3. C.Each connection takes about two to three months, with the mapping document as the heaviest step
  4. D.EDI cannot carry invoices
Answer: C
Each connection takes about two to three months, with the mapping document as the heaviest step

Each connection takes about two to three months, with the mapping document as the heaviest step. The setup investment pays back only over sustained volume.

Source: answer explanations, p. 78
QUESTION 234R · PDF p. 52

Which port system manages yard positions, crane dispatch and vessel work planning?

  1. A.Port Community System (PCS)
  2. B.ePort customer portal
  3. C.ASEAN Single Window
  4. D.Terminal Operating System (TOS)
Answer: D
Terminal Operating System (TOS)

Terminal Operating System (TOS). PCS connects the parties; ePort serves customers; the single window serves customs.

Source: answer explanations, p. 78
QUESTION 235U · PDF p. 52

The main difference between EDI and API is…

  1. A.EDI is newer than API
  2. B.API requires a bilateral mapping document of several months
  3. C.EDI is free while API always charges per message through a VAN
  4. D.EDI exchanges documents in batches on a cycle; API supports real-time request and response
Answer: D
EDI exchanges documents in batches on a cycle; API supports real-time request and response

EDI exchanges documents in batches on a cycle; API supports real-time request and response. Real firms run both for different purposes.

Source: answer explanations, p. 78
QUESTION 236U · PDF p. 52

For tracking 1,000 shipments a day, why is a webhook usually preferable to polling?

  1. A.Webhooks are a type of barcode
  2. B.Polling is illegal
  3. C.Webhooks require no internet connection
  4. D.The provider pushes an update only when an event occurs, avoiding wasted calls and rate-limit blocking
Answer: D
The provider pushes an update only when an event occurs, avoiding wasted calls and rate-limit blocking

The provider pushes an update only when an event occurs, avoiding wasted calls and rate-limit blocking. Event-driven integration scales better than repeated queries.

Source: answer explanations, p. 78
QUESTION 237R · PDF p. 53

Which system lets traders declare once on one portal so that ministries reuse the same data?

  1. A.The National Single Window
  2. B.A private CRM
  3. C.A WMS
  4. D.A Terminal Operating System
Answer: A
The National Single Window

The National Single Window. VNACCS/VCIS handles customs clearance; the ASEAN Single Window links national portals.

Source: answer explanations, p. 78
QUESTION 238R · PDF p. 53

In risk-based customs channelling, the red channel means…

  1. A.automatic clearance with no checks
  2. B.physical inspection of the goods
  3. C.document inspection only
  4. D.refund of duty
Answer: B
physical inspection of the goods

physical inspection of the goods. Green = automatic, yellow = documents, red = physical.

Source: answer explanations, p. 78
QUESTION 239U · PDF p. 53

Under Vietnam’s mandatory e-invoicing, how must an incorrect invoice be handled by the ERP?

  1. A.By printing a paper copy
  2. B.By an adjustment or replacement invoice – never by deletion
  3. C.By deleting it from the database
  4. D.By editing the signed file directly
Answer: B
By an adjustment or replacement invoice – never by deletion

By an adjustment or replacement invoice – never by deletion. Signed invoices are retained for the statutory period; corrections leave an audit trail.

Source: answer explanations, p. 78
QUESTION 240An · PDF p. 53

What is the main barrier to adopting the electronic Bill of Lading?

  1. A.Legal recognition and participation of all parties, not technology – as TradeLens’s closure in 2023 showed
  2. B.Weak encryption algorithms
  3. C.Insufficient bandwidth
  4. D.Inability to track containers
Answer: A
Legal recognition and participation of all parties, not technology – as TradeLens’s closure in 2023 showed

Legal recognition and participation of all parties, not technology – as TradeLens’s closure in 2023 showed. Title must be unique and legally recognised; one holdout forces paper.

Source: answer explanations, p. 78
SESSION 13 / 15

MIS in operations

Questions 241–260 · 20 questions

QUESTION 241U · PDF p. 53

According to the lecture, where does the value of a logistics MIS mainly lie?

  1. A.In the most expensive single module
  2. B.In the number of screens
  3. C.In the integration between systems – the lines between the boxes
  4. D.In the hardware brand
Answer: C
In the integration between systems – the lines between the boxes

In the integration between systems – the lines between the boxes. Disconnected systems do not create end-to-end value.

Source: answer explanations, p. 79
QUESTION 242U · PDF p. 53

Why should information flow run ahead of the physical flow?

  1. A.Customers prefer not to know about delays
  2. B.It reduces the weight of shipments
  3. C.Goods move faster when paperwork is slower
  4. D.Information that arrives before the goods allows planning (rescheduling, warning the customer) rather than mere reaction
Answer: D
Information that arrives before the goods allows planning (rescheduling, warning the customer) rather than mere reaction

Information that arrives before the goods allows planning (rescheduling, warning the customer) rather than mere reaction. A delay reported at departure lets the warehouse and customer adjust.

Source: answer explanations, p. 79
QUESTION 243U · PDF p. 54

Which interface design rule prevents two systems’ data from diverging?

  1. A.Avoid error handling to keep it simple
  2. B.Always use two-way synchronisation
  3. C.Allow every system to edit every field
  4. D.One owner per data type – only one system may edit a given field
Answer: D
One owner per data type – only one system may edit a given field

One owner per data type – only one system may edit a given field. Two editors of one field inevitably diverge.

Source: answer explanations, p. 79
QUESTION 244R · PDF p. 54

The four master data domains every transaction points at are…

  1. A.CPU, memory, disk, network
  2. B.orders, receipts, invoices, payments
  3. C.item, partner, location, price and rate
  4. D.awareness, desire, knowledge, ability
Answer: C
item, partner, location, price and rate

item, partner, location, price and rate. Orders, receipts and invoices are transactions, not master data.

Source: answer explanations, p. 79
QUESTION 245Ap · PDF p. 54

One customer exists under three codes in the partner master. What breaks first?

  1. A.Credit control and any report by customer
  2. B.The barcode printer
  3. C.The GPS signal of trucks
  4. D.The warehouse temperature
Answer: A
Credit control and any report by customer

Credit control and any report by customer. Exposure is split across codes, so limits and reports are wrong.

Source: answer explanations, p. 79
QUESTION 246Ap · PDF p. 54

In an exception playbook, a reefer temperature breach detected by an IoT sensor should have…

  1. A.a monthly review only
  2. B.shared responsibility across all departments with no deadline
  3. C.no action until the customer complains
  4. D.one named owner (the dispatcher) and deadlines for each action, e.g. call the driver within 15 minutes
Answer: D
one named owner (the dispatcher) and deadlines for each action, e.g. call the driver within 15 minutes

one named owner (the dispatcher) and deadlines for each action, e.g. call the driver within 15 minutes. Shared responsibility is no responsibility; every step needs a deadline.

Source: answer explanations, p. 79
QUESTION 247R · PDF p. 54

The four capabilities of a logistics control tower are…

  1. A.plan, do, check and act
  2. B.receiving, storing, picking and shipping
  3. C.visibility, monitoring, alerting and response
  4. D.extract, transform, load and verify
Answer: C
visibility, monitoring, alerting and response

visibility, monitoring, alerting and response. See, monitor, alert, respond – from one place.

Source: answer explanations, p. 79
QUESTION 248U · PDF p. 54

Why does management by exception scale?

  1. A.Managers personally check every shipment
  2. B.The system watches every shipment and surfaces only threshold breaches, turning an ocean of data into a short action list
  3. C.It removes the need for KPIs
  4. D.Exceptions are ignored
Answer: B
The system watches every shipment and surfaces only threshold breaches, turning an ocean of data into a short action list

The system watches every shipment and surfaces only threshold breaches, turning an ocean of data into a short action list. One manager cannot watch thousands of shipments.

Source: answer explanations, p. 79
QUESTION 249U · PDF p. 54

What happens if alert thresholds are set too tight?

  1. A.The database stops working
  2. B.Costs automatically fall
  3. C.Users are flooded with alerts and start ignoring them
  4. D.Problems are missed entirely
Answer: C
Users are flooded with alerts and start ignoring them

Users are flooded with alerts and start ignoring them. Too loose misses problems; setting thresholds is a business task.

Source: answer explanations, p. 79
QUESTION 250R · PDF p. 55

Which is NOT one of the four dashboard design rules?

  1. A.Show every available metric on one screen
  2. B.Always include a comparison (target, prior period or benchmark)
  3. C.“If this is bad, what do I do?” – otherwise remove the metric
  4. D.One role, one question
Answer: A
Show every available metric on one screen

Show every available metric on one screen. Five to seven components maximum; a good dashboard has been cut back many times.

Source: answer explanations, p. 79
QUESTION 251R · PDF p. 55

OTIF is calculated as…

  1. A.(on-time rate + in-full rate) ÷ 2
  2. B.orders delivered both on time and in full ÷ total orders
  3. C.COGS ÷ average inventory
  4. D.units delivered ÷ units ordered
Answer: B
orders delivered both on time and in full ÷ total orders

orders delivered both on time and in full ÷ total orders. OTIF is a product condition per order, not an average of two rates.

Source: answer explanations, p. 79
QUESTION 252Ap · PDF p. 55

Of 1,000 orders, 920 were on time; of those, 870 were also complete. What is OTIF?

  1. A.95%
  2. B.87%
  3. C.92%
  4. D.89.5%
Answer: B
87%

87%. 870 ÷ 1,000 = 87%.

Source: answer explanations, p. 79
QUESTION 253U · PDF p. 55

Which is the main trap of the fill-rate metric?

  1. A.It depends on warehouse temperature
  2. B.It cannot be expressed as a percentage
  3. C.It double-counts late orders
  4. D.It measures completeness only, not timing
Answer: D
It measures completeness only, not timing

It measures completeness only, not timing. A complete but late delivery still scores 100% fill rate.

Source: answer explanations, p. 79
QUESTION 254Ap · PDF p. 55

On-time, in-full, undamaged and correct documents are each 97%. What is the perfect order rate?

  1. A.About 88.5%
  2. B.About 91%
  3. C.About 94%
  4. D.97%
Answer: A
About 88.5%

About 88.5%. 0.97⁴ ≈ 0.885, which is why it tells the honest truth.

Source: answer explanations, p. 79
QUESTION 255Ap · PDF p. 55

Annual COGS is 12 billion VND and average inventory is 2 billion VND. What are inventory turns and days of inventory?

  1. A.6 turns; about 6 days
  2. B.6 turns; about 61 days
  3. C.24 turns; about 15 days
  4. D.0.17 turns; about 2,190 days
Answer: B
6 turns; about 61 days

6 turns; about 61 days. 12 ÷ 2 = 6 turns; 365 ÷ 6 ≈ 60.8 days. Turns are comparable only within an industry.

Source: answer explanations, p. 79
QUESTION 256R · PDF p. 55

Which analytics level answers “What should we do?”

  1. A.Descriptive
  2. B.Predictive
  3. C.Prescriptive
  4. D.Diagnostic
Answer: C
Prescriptive

Prescriptive. Optimisation and simulation recommend actions.

Source: answer explanations, p. 79
QUESTION 257Ap · PDF p. 56

“There is a 70% chance this shipment will be late” is an output of which analytics level?

  1. A.Predictive
  2. B.Diagnostic
  3. C.Descriptive
  4. D.Prescriptive
Answer: A
Predictive

Predictive. It estimates what will happen.

Source: answer explanations, p. 79
QUESTION 258U · PDF p. 56

Why use a balanced scorecard rather than cost metrics alone?

  1. A.Measuring only cost lets managers cut it by degrading service; four perspectives (financial, customer, process, learning) expose the trade-off
  2. B.Law requires four perspectives
  3. C.Scorecards replace all dashboards
  4. D.Cost cannot be measured
Answer: A
Measuring only cost lets managers cut it by degrading service; four perspectives (financial, customer, process, learning) expose the trade-off

Measuring only cost lets managers cut it by degrading service; four perspectives (financial, customer, process, learning) expose the trade-off. Balanced measures keep service and capability in view.

Source: answer explanations, p. 79
QUESTION 259R · PDF p. 56

Which sequence is the PDCA improvement loop?

  1. A.Pilot → Develop → Check → Archive
  2. B.Predict → Decide → Control → Analyse
  3. C.Prepare → Deploy → Close → Audit
  4. D.Plan → Do → Check → Act
Answer: D
Plan → Do → Check → Act

Plan → Do → Check → Act. MIS supplies honest data for the Check step.

Source: answer explanations, p. 79
QUESTION 260An · PDF p. 56

In Lab 13, some orders have an actual delivery date earlier than the order date. What is the correct treatment?

  1. A.Replace the dates with today’s date
  2. B.Delete them from the original file without a record
  3. C.Exclude them from the OTIF calculation, flag them for verification and record them in the cleaning log, leaving the Raw sheet unchanged
  4. D.Count them as on time
Answer: C
Exclude them from the OTIF calculation, flag them for verification and record them in the cleaning log, leaving the Raw sheet unchanged

Exclude them from the OTIF calculation, flag them for verification and record them in the cleaning log, leaving the Raw sheet unchanged. Traceable, reproducible cleaning is required by CLO 2.2 and the lab rubric.

Source: answer explanations, p. 80
SESSION 14 / 15

IS projects and resources

Questions 261–280 · 20 questions

QUESTION 261R · PDF p. 56

According to typical industry surveys cited in the lecture, roughly what share of IS projects run over budget or late?

  1. A.None
  2. B.About one-tenth
  3. C.About two-thirds
  4. D.About 5%
Answer: C
About two-thirds

About two-thirds. About one-fifth are cancelled outright; the figures are indicative.

Source: answer explanations, p. 80
QUESTION 262U · PDF p. 56

What do almost all root causes of IS project failure have in common?

  1. A.They are caused by slow processors
  2. B.They are unpredictable natural events
  3. C.They concern people, organisation and management rather than hardware or software
  4. D.They are caused by programming languages
Answer: C
They concern people, organisation and management rather than hardware or software

They concern people, organisation and management rather than hardware or software. The five-component lesson from Session 1 again.

Source: answer explanations, p. 80
QUESTION 263R · PDF p. 57

Which is NOT part of the triple constraint?

  1. A.Time
  2. B.Scope
  3. C.Cost
  4. D.Technology
Answer: D
Technology

Technology. The three are scope, time and cost.

Source: answer explanations, p. 80
QUESTION 264U · PDF p. 57

Features are added to a WMS project while the date and budget stay fixed. What typically happens?

  1. A.Quality suffers, usually because testing is cut
  2. B.The project finishes early
  3. C.Quality improves automatically
  4. D.Nothing changes
Answer: A
Quality suffers, usually because testing is cut

Quality suffers, usually because testing is cut. The PM’s job is to make the trade-off explicit.

Source: answer explanations, p. 80
QUESTION 265U · PDF p. 57

Which practice best controls scope creep?

  1. A.Accepting all small requests without assessment
  2. B.Letting developers decide additions
  3. C.Refusing all changes forever
  4. D.Out-of-scope list in the charter, impact assessment of every request and sponsor approval with an explicit trade-off
Answer: D
Out-of-scope list in the charter, impact assessment of every request and sponsor approval with an explicit trade-off

Out-of-scope list in the charter, impact assessment of every request and sponsor approval with an explicit trade-off. “Which item do we drop to make room?” turns conflict into a trade-off.

Source: answer explanations, p. 80
QUESTION 266R · PDF p. 57

The 8–80 rule for WBS work packages means each package should take…

  1. A.between 8 and 80 hours of effort
  2. B.between 8 and 80 days
  3. C.8 people and 80 hours
  4. D.8% to 80% of the budget
Answer: A
between 8 and 80 hours of effort

between 8 and 80 hours of effort. Smaller is micromanagement; larger is uncontrollable.

Source: answer explanations, p. 80
QUESTION 267U · PDF p. 57

An activity on the critical path…

  1. A.is always the cheapest task
  2. B.can slip freely without consequence
  3. C.has zero float, so a day lost on it delays the whole project by a day
  4. D.is never dependent on other tasks
Answer: C
has zero float, so a day lost on it delays the whole project by a day

has zero float, so a day lost on it delays the whole project by a day. Float measures how long a task can slip harmlessly.

Source: answer explanations, p. 80
QUESTION 268Ap · PDF p. 57

A (3 days) starts the project; B (5 days) and C (2 days) both follow A; D (4 days) follows B and C. What is the project duration?

  1. A.14 days
  2. B.9 days
  3. C.10 days
  4. D.12 days
Answer: D
12 days

12 days. Critical path A–B–D = 3 + 5 + 4 = 12 days.

Source: answer explanations, p. 80
QUESTION 269Ap · PDF p. 57

In the same network, what is the float of activity C?

  1. A.0 days
  2. B.5 days
  3. C.3 days
  4. D.2 days
Answer: C
3 days

3 days. ES(C) = 3, LS(C) = LF − d = 8 − 2 = 6; float = 6 − 3 = 3.

Source: answer explanations, p. 80
QUESTION 270R · PDF p. 58

In a RACI matrix, “A” stands for…

  1. A.Advising
  2. B.Assisting
  3. C.Accountable – owns the outcome; exactly one per task
  4. D.Approving by committee
Answer: C
Accountable – owns the outcome; exactly one per task

Accountable – owns the outcome; exactly one per task. R does the work, C is consulted, I is informed.

Source: answer explanations, p. 80
QUESTION 271Ap · PDF p. 58

A RACI row for “approve go-live” lists both the PM and the sponsor as A. What is wrong?

  1. A.Each row must have exactly one Accountable person; here it should be the sponsor
  2. B.The row should list only I’s
  3. C.There should be no A at all
  4. D.Nothing; two A’s improve control
Answer: A
Each row must have exactly one Accountable person; here it should be the sponsor

Each row must have exactly one Accountable person; here it should be the sponsor. Two owners recreate “I thought you were doing it.”

Source: answer explanations, p. 80
QUESTION 272R · PDF p. 58

The four risk response strategies are…

  1. A.plan, do, check and act
  2. B.avoid, mitigate, transfer and accept
  3. C.big bang, phased, parallel and pilot
  4. D.must, should, could and won’t
Answer: B
avoid, mitigate, transfer and accept

avoid, mitigate, transfer and accept. Mitigate is the most used.

Source: answer explanations, p. 80
QUESTION 273Ap · PDF p. 58

A contractual penalty clause for late vendor configuration is an example of which response?

  1. A.Mitigate by training
  2. B.Avoid
  3. C.Transfer
  4. D.Accept
Answer: C
Transfer

Transfer. The financial consequence is shifted by contract; the risk does not vanish.

Source: answer explanations, p. 80
QUESTION 274Ap · PDF p. 58

A risk has likelihood 3 and impact 3 on 1–3 scales. What is its score?

  1. A.9
  2. B.3
  3. C.6
  4. D.1
Answer: A
9

9. Score = likelihood × impact = 9, the highest priority.

Source: answer explanations, p. 80
QUESTION 275R · PDF p. 58

Which statement about the Scrum master is correct?

  1. A.Writes all the code
  2. B.Removes blockers and coaches the team; is not the boss
  3. C.Sets and prioritises the product backlog
  4. D.Approves the budget
Answer: B
Removes blockers and coaches the team; is not the boss

Removes blockers and coaches the team; is not the boss. The product owner prioritises the backlog.

Source: answer explanations, p. 80
QUESTION 276U · PDF p. 58

Which Agile ceremony is most often skipped, although it is the only one that improves the team itself?

  1. A.The retrospective
  2. B.The sprint review demo
  3. C.Sprint planning
  4. D.The daily stand-up
Answer: A
The retrospective

The retrospective. Continue, stop, try – focus on process, not blame.

Source: answer explanations, p. 80
QUESTION 277R · PDF p. 59

How does an RFI differ from an RFP?

  1. A.They are identical
  2. B.An RFI surveys the market non-bindingly; an RFP states the need and requests formal proposals
  3. C.An RFP is sent after the contract is signed
  4. D.An RFI is a payment request
Answer: B
An RFI surveys the market non-bindingly; an RFP states the need and requests formal proposals

An RFI surveys the market non-bindingly; an RFP states the need and requests formal proposals. An RFP should state the need, not the solution.

Source: answer explanations, p. 80
QUESTION 278U · PDF p. 59

Which contract clause do beginners most often forget?

  1. A.The colour of the user interface
  2. B.The vendor’s logo placement
  3. C.Data ownership and the right to extract your own data
  4. D.The number of meetings per week
Answer: C
Data ownership and the right to extract your own data

Data ownership and the right to extract your own data. Without it the firm is locked in permanently.

Source: answer explanations, p. 80
QUESTION 279U · PDF p. 59

Under a hybrid sourcing model for IT talent, what should be kept in-house?

  1. A.Only the help-desk telephone
  2. B.Everything, always
  3. C.Core capabilities that give advantage and work touching sensitive data
  4. D.Nothing; outsource all IT
Answer: C
Core capabilities that give advantage and work touching sensitive data

Core capabilities that give advantage and work touching sensitive data. Flex the rest through outsourcing.

Source: answer explanations, p. 80
QUESTION 280An · PDF p. 59

A project reported green for eight weeks, then suddenly red. Why is this “watermelon reporting” damaging, and what is the remedy?

  1. A.It hides slippage until options are gone and destroys trust; report amber early with issues and a decision needed by a date
  2. B.It is harmless because the project ends anyway
  3. C.The remedy is to stop reporting
  4. D.Colours are irrelevant to management
Answer: A
It hides slippage until options are gone and destroys trust; report amber early with issues and a decision needed by a date

It hides slippage until options are gone and destroys trust; report amber early with issues and a decision needed by a date. Reporting bad news early is one of the most valued skills.

Source: answer explanations, p. 80
SESSION 15 / 15

Trends and the digital future

Questions 281–300 · 20 questions

QUESTION 281R · PDF p. 59

Which four technology trends are highlighted as reshaping logistics?

  1. A.Fax, pagers, CDs and floppy disks
  2. B.Artificial intelligence, blockchain, digital twin, autonomous systems and robotics
  3. C.EDI, barcode, spreadsheets and email
  4. D.LAN, WAN, PAN and MAN
Answer: B
Artificial intelligence, blockchain, digital twin, autonomous systems and robotics

Artificial intelligence, blockchain, digital twin, autonomous systems and robotics. Their power lies in combination, but adoption starts with a single payback.

Source: answer explanations, p. 81
QUESTION 282U · PDF p. 59

What is the main barrier to blockchain adoption in logistics?

  1. A.Blockchain is too easy to rewrite
  2. B.Participation of enough parties, not the technology
  3. C.Blockchain cannot store any data
  4. D.It requires paper documents
Answer: B
Participation of enough parties, not the technology

Participation of enough parties, not the technology. A shared ledger is valuable only if the parties join.

Source: answer explanations, p. 81
QUESTION 283U · PDF p. 60

Where do most AI projects in logistics fail?

  1. A.On excessive data quality
  2. B.On insufficient monitor resolution
  3. C.On choosing the wrong programming language
  4. D.On the lack of clean historical data, not on algorithms
Answer: D
On the lack of clean historical data, not on algorithms

On the lack of clean historical data, not on algorithms. A defined action process and domain review are also required.

Source: answer explanations, p. 81
QUESTION 284R · PDF p. 60

Which data does AI demand forecasting require, according to the lecture?

  1. A.Driver ages
  2. B.Two or more years of sales history, promotions, holidays and prices
  3. C.Warehouse floor colour
  4. D.Only today’s orders
Answer: B
Two or more years of sales history, promotions, holidays and prices

Two or more years of sales history, promotions, holidays and prices. Demand forecasting is a mature use case when history is available.

Source: answer explanations, p. 81
QUESTION 285U · PDF p. 60

Which caution applies to generative AI in logistics?

  1. A.It is fluent but can make confident errors, so outputs with financial or legal consequences need human verification
  2. B.It cannot draft documents
  3. C.It never makes mistakes
  4. D.It replaces all ERP systems
Answer: A
It is fluent but can make confident errors, so outputs with financial or legal consequences need human verification

It is fluent but can make confident errors, so outputs with financial or legal consequences need human verification. Draft customs forms and emails still require review.

Source: answer explanations, p. 81
QUESTION 286Ap · PDF p. 60

Emissions from subcontracted trucking and ocean carriage fall under…

  1. A.Scope 2
  2. B.Scope 3
  3. C.Scope 1
  4. D.No scope
Answer: B
Scope 3

Scope 3. Scope 3 covers the value chain and is usually the largest and hardest.

Source: answer explanations, p. 81
QUESTION 287Ap · PDF p. 60

Electricity purchased to run a cold store falls under…

  1. A.Scope 3
  2. B.Scope 1
  3. C.Scope 2
  4. D.Scope 4
Answer: C
Scope 2

Scope 2. Scope 2 covers purchased energy.

Source: answer explanations, p. 81
QUESTION 288R · PDF p. 60

Which framework and intensity unit are used for logistics emissions reporting in the lecture?

  1. A.GLEC Framework; g CO₂e per tonne-km
  2. B.PMBOK; hours per task
  3. C.ITIL; tickets per day
  4. D.ISO 9001; kg per pallet
Answer: A
GLEC Framework; g CO₂e per tonne-km

GLEC Framework; g CO₂e per tonne-km. Activity data × emission factors → CO₂e → intensity.

Source: answer explanations, p. 81
QUESTION 289U · PDF p. 60

Why are green-logistics levers attractive to leadership?

  1. A.They always increase revenue by 50%
  2. B.They eliminate the need for vehicles
  3. C.They require no data
  4. D.Route optimisation, higher fill, modal shift and backhaul matching cut both carbon and cost
Answer: D
Route optimisation, higher fill, modal shift and backhaul matching cut both carbon and cost

Route optimisation, higher fill, modal shift and backhaul matching cut both carbon and cost. Green and efficient logistics are usually the same thing.

Source: answer explanations, p. 81
QUESTION 290R · PDF p. 61

Which sequence describes the autonomous supply chain loop?

  1. A.Predict → Ignore → Decide → Wait
  2. B.Sense → Predict → Decide → Act
  3. C.Act → Sense → Report → Archive
  4. D.Plan → Buy → Store → Sell
Answer: B
Sense → Predict → Decide → Act

Sense → Predict → Decide → Act. It runs continuously with humans supervising.

Source: answer explanations, p. 81
QUESTION 291U · PDF p. 61

Where does autonomy realistically reach today?

  1. A.Negotiating key customer contracts
  2. B.Repetitive, rule-based, low-risk decisions such as threshold replenishment
  3. C.All strategic decisions including mergers
  4. D.Deciding staff dismissals
Answer: B
Repetitive, rule-based, low-risk decisions such as threshold replenishment

Repetitive, rule-based, low-risk decisions such as threshold replenishment. High-risk and relationship-affecting calls still need a person.

Source: answer explanations, p. 81
QUESTION 292R · PDF p. 61

Which sequence gives the three levels of digital twin maturity?

  1. A.Simulation → true twin → static model
  2. B.True twin → static model → simulation
  3. C.Spreadsheet → ERP → CRM
  4. D.Static model → simulation → true digital twin
Answer: D
Static model → simulation → true digital twin

Static model → simulation → true digital twin. Most real value sits at the simulation level.

Source: answer explanations, p. 81
QUESTION 293U · PDF p. 61

What is the prerequisite for warehouse simulation or a digital twin?

  1. A.A 3D printer
  2. B.A blockchain ledger
  3. C.Time-stamped data for each process step, not just per order
  4. D.A larger marketing budget
Answer: C
Time-stamped data for each process step, not just per order

Time-stamped data for each process step, not just per order. A firm that cannot measure steps cannot simulate them.

Source: answer explanations, p. 81
QUESTION 294R · PDF p. 61

Which sequence is the digital maturity ladder?

  1. A.Autonomous → Manual → Integrated → Digitised → Data-driven
  2. B.Integrated → Manual → Autonomous → Digitised → Data-driven
  3. C.Manual → Digitised → Integrated → Data-driven → Autonomous
  4. D.Digitised → Autonomous → Manual → Data-driven → Integrated
Answer: C
Manual → Digitised → Integrated → Data-driven → Autonomous

Manual → Digitised → Integrated → Data-driven → Autonomous. Rungs cannot be skipped.

Source: answer explanations, p. 81
QUESTION 295Ap · PDF p. 61

A firm has ERP and WMS in place but they are not connected, and reports are compiled in Excel. What is its maturity rung and its next step?

  1. A.Digitised; next, integrate the systems so they share data
  2. B.Manual; next, deploy AI agents immediately
  3. C.Data-driven; next, remove the WMS
  4. D.Autonomous; next, return to paper
Answer: A
Digitised; next, integrate the systems so they share data

Digitised; next, integrate the systems so they share data. Core systems exist but are separate – rung 2; climb one rung at a time.

Source: answer explanations, p. 81
QUESTION 296U · PDF p. 61

What is the recommended defence against business email compromise asking you to pay a supplier’s “new” bank account?

  1. A.Forward it to all staff
  2. B.Reply to the email to ask whether it is genuine
  3. C.Confirm any bank-detail change by phone on a previously stored number
  4. D.Pay quickly to avoid penalties
Answer: C
Confirm any bank-detail change by phone on a previously stored number

Confirm any bank-detail change by phone on a previously stored number. The attacker controls the email channel, so verification must be out-of-band.

Source: answer explanations, p. 81
QUESTION 297U · PDF p. 62

In the 3-2-1 backup rule emphasised against ransomware, which copy is described as the one that saves you?

  1. A.The copy on an employee’s email
  2. B.The offline copy
  3. C.The copy on the same server
  4. D.There is no need for any copy
Answer: B
The offline copy

The offline copy. Ransomware can encrypt connected backups; tested restores are essential.

Source: answer explanations, p. 81
QUESTION 298R · PDF p. 62

Which set lists the four ethical principles proposed in the lecture?

  1. A.Transparency, fairness, accountability, data minimisation
  2. B.Speed, scale, secrecy, surveillance
  3. C.Profit, growth, automation, outsourcing
  4. D.Must, should, could, won’t
Answer: A
Transparency, fairness, accountability, data minimisation

Transparency, fairness, accountability, data minimisation. Accountability always rests with a named human.

Source: answer explanations, p. 81
QUESTION 299U · PDF p. 62

Among the seven questions for evaluating a technology, which one eliminates most proposals?

  1. A.Do competitors talk about it?
  2. B.Is the interface attractive?
  3. C.Is the vendor famous?
  4. D.Do we have the data and infrastructure?
Answer: D
Do we have the data and infrastructure?

Do we have the data and infrastructure?. The other questions concern the problem, baseline, users, TCO, exit and small tests.

Source: answer explanations, p. 81
QUESTION 300An · PDF p. 62

An AI system automatically switches to a backup supplier, and the switch causes a loss. Who is accountable?

  1. A.The firm and the named people who designed, approved and supervise the rule – responsibility stays with people
  2. B.Nobody, because it was automatic
  3. C.The AI system itself
  4. D.The backup supplier alone
Answer: A
The firm and the named people who designed, approved and supervise the rule – responsibility stays with people

The firm and the named people who designed, approved and supervise the rule – responsibility stays with people. Automation does not transfer accountability; pre-approval and supervision are human duties.

Source: answer explanations, p. 82